Laserfiche WebLink
Proposed Remedial Excavation: 4849 Spire Lane, Everett, WA <br />December 8, 2022 <br />Variations in soil conditions may exist between what was anticipated and the actual <br />conditions underlying the site. The nature and extent of soil variations may not be evident <br />until construction occurs. If any soil conditions are encountered at the site that are different <br />from those described in this report, we should be notified immediately to review the <br />applicability of our recommendations. Additionally, we should also be notified to review <br />the applicability of our recommendations if there are any changes in the project scope. <br />The scope of our work does not include services related to construction safety precautions. <br />Our recommendations are not intended to direct the contractors' methods, techniques, <br />sequences or procedures, except as specifically described in our report for consideration in <br />design. Additionally, the scope of our work specifically excludes the assessment of <br />environmental characteristics, particularly those involving hazardous substances. We are <br />not mold consultants nor are our recommendations to be interpreted as being preventative <br />of mold development. A mold specialist should be consulted for all mold -related issues. <br />This report has been prepared for planning and design purposes for specific application to <br />the proposed project in accordance with the generally accepted standards of local practice <br />at the time this report was written. No warranty, express or implied, is made. <br />This report may be used only by the client and for the purposes stated, within a reasonable <br />time from its issuance. Land use, site conditions (both off and on -site), or other factors <br />including advances in our understanding of applied science, may change over time and <br />could materially affect our findings. Therefore, this report should not be relied upon after <br />24 months from its issuance. PanGEO should be notified if the project is delayed by more <br />than 24 months from the date of this report so that we may review the applicability of our <br />conclusions considering the time lapse. <br />It is the client's responsibility to see that all parties to this project, including the designer, <br />contractor, subcontractors, etc., are made aware of this report in its entirety. The use of <br />information contained in this report for bidding purposes should be done at the contractor's <br />option and risk. Any party other than the client who wishes to use this report shall notify <br />PanGEO of such intended use and for permission to copy this report. Based on the intended <br />use of the report, PanGEO may require that additional work be performed and that air <br />updated report be reissued. Noncompliance with any of these requirements will release <br />PanGEO from any liability resulting from the use this report. <br />22-389�4849 spire lane everett_apt.docx Page l l PanGEO, Inc. <br />