Construction Milestones <br />Phases Date <br />Preliminary Engineering Start Date Nov-25 <br />Environmental Documents (NEPA/SEPA) Jul-29 <br />Right of Way Certification Jan-30 <br />Contract Award Date Aug-25 <br />Construction Operationally Complete Jun-34 <br />Everett Transit <br />PTD1163 <br />2 of 25