<br />00 72 00 - 31 GENERAL CONDITIONS
<br />8.6.4. Inspection at Point of Manufacturing
<br />The Contractor shall be responsible and reimburse the Owner for the costs of inspections occurring
<br />outside of Whatcom, Skagit, Island, Snohomish, King, Pierce and Thurston counties if (a) inspection and
<br />testing of materials or Equipment in the vicinity of the Work by the Owner is not practicable, (b) the
<br />Contractor requests the Owner to inspect and test material or Equipment at the point of manufacture, or
<br />(c) the Specifications require that inspection, testing or witnessing of tests take place at the point of
<br />manufacture. Costs to be paid or reimbursed by the Contractor include, but are not limited to, travel,
<br />subsistence, labor and lodging expenses of the Owner’s inspector.
<br />8.6.5. Testing and Commissioning of Completed Work
<br />Testing and commissioning of all mechanical, electrical, and instrumentation systems and completed
<br />portions of the Work, functioning as a completed system and the complete Project, functioning as a
<br />completed facility, shall be done in accordance with the Specifications.
<br />8.6.6. Storage of Materials and Equipment
<br />Contractor shall store materials and Equipment so as to insure the preservation of their quality and fitness
<br />for the Work. Stored Equipment and materials shall be located so as to facilitate inspection. The
<br />Contractor shall be responsible for damages, loss or casualty occurring to materials and Equipment until
<br />Final Acceptance.
<br />8.6.7. Manufacturer's Directions
<br />Manufactured articles, material and Equipment shall be transported, stored, applied, installed, connected,
<br />erected, adjusted, tested, operated and maintained as recommended by the manufacturer, unless otherwise
<br />specified herein. Manufacturer's installation instructions and procedures shall be provided to the Owner
<br />prior to installation of the manufactured articles, material and Equipment.
<br />8.7. DEFECTIVE WORK
<br />8.7.1. Correction of Defective Work
<br />When, and as often as the Owner’s Representative determines through his or her inspection procedures,
<br />material, Equipment or workmanship incorporated in the Project do not meet the requirements of the
<br />Contract, the Owner’s Representative will give written notice of the noncompliance to the Contractor.
<br />Within fourteen (14) days from the receipt of such notice, the Contractor shall undertake the Work
<br />necessary to correct the deficiencies, and to comply with the Contract. If the Contractor disagrees with
<br />the Owner’s Representative's determination and believes that the corrective Work should be covered by a
<br />Change Order, he or she shall immediately notify the Owner, in writing, setting forth its position. Within
<br />five (5) days after receipt of the Contractor's notification, the Owner will review the matter and notify the
<br />Contractor, in writing, of his or her determination.
<br />If the Owner determines that the corrective Work is required to comply with the Contract, the Contractor
<br />shall proceed with such Work. As a condition precedent to the Contractor's request for adjustment of
<br />Contract Sum, Contract Time, or both, resulting from the performance of such corrective Work, the
<br />Contractor shall, within fifteen (15) days after receipt of the Owner's determination, provide the Owner
<br />with Notice of a Contract Claim for an adjustment of Contract Sum, Contract Time, or both. Contract
<br />Claims not timely and completely submitted are deemed waived. The Contractor shall document the cost
<br />information associated with the corrective work with daily records in accordance with Force Account
<br />procedures and shall provide such information to the Owner’s Representative daily. Receipt of the cost
<br />data by the Owner’s Representative will not be construed to be an acceptance of the corrective Work, or
<br />an authorization for a Change Order to cover the corrective Work. Contractor waives any such Contract
<br />Claim by failing to maintain accurate and complete Force Account records.
|