City of Everett 00 72 00 - 38 <br />Port Gardner Storage Facility – Facility Construction Package WO# UP-3525 <br /> <br /> <br />00 72 00 - 38 GENERAL CONDITIONS <br />4. The total payment for any one item in the case of a deletion or partial termination shall not exceed <br />the Bid price as modified by approved Change Orders less the estimated cost, including Overhead <br />and profit, to complete the Work and less any amount paid to the Contractor for the item; <br />5. If the entire remainder of the Contract is terminated, the total payment to the Contractor shall not <br />exceed the total Contract Sum as modified by approved Change Orders less those amounts paid to <br />the Contractor before the effective date of the termination; and <br />6. No claim for damages of any kind or for loss of anticipated profits or consequential damages on <br />deleted or terminated Work will be allowed because of termination or Change Order. Contract <br />Time shall be adjusted as the parties agree. If the parties cannot agree, the Owner’s <br />Representative will determine the adjustment of Contract Time. <br />Acceptable materials ordered by the Contractor prior to the date the Work was terminated or deleted will <br />either be purchased from the Contractor by the Owner at the actual cost and shall become the property of <br />the Owner, or the Owner will reimburse the Contractor for the actual costs of returning these materials to <br />the Suppliers. <br />If Contractor disagrees with the adjustment of Contract Sum determined by the Owner’s Representative, <br />Contractor may submit a Contract Claim for the difference between the amount determined by the <br />Owner’s Representative and the amount sought by the Contractor. <br />Contractor shall not be entitled to anticipated profits on deleted, terminated, or uncompleted Work. <br />9.3. CHARGES TO CONTRACTOR <br />The Contractor shall pay the Owner on demand everything charged to it under the terms of this Contract. <br />Such charges may be deducted by the Owner from money due or to become due to the Contractor under <br />the Contract. The Owner may recover such charges from the Contractor or from its surety. <br />Contractor agrees to pay the costs of overtime or excessive inspection and observation costs incurred by <br />the Owner. Overtime inspection shall include inspection required during Saturdays, Sundays, City <br />holidays and weekdays, in excess of 40 hours per week or outside of normal working hours and <br />inspections or observations that result in an inspector or observer working more than forty hours in a <br />week. Costs of such overtime or excessive inspection or observation include architecture, engineering, <br />construction management services, inspection, general supervision and Overhead expenses which are <br />directly chargeable to the overtime or excessive work. Contractor agrees that Owner will deduct such <br />charges from payments due the Contractor. In the event the Owner by Change Order requires the <br />Contractor to work in excess of the established schedule of working hours, the Owner will not charge the <br />Contractor for inspection costs associated therewith. <br />9.4. COMPENSATION TO OWNER FOR TIME EXTENSION <br />The Owner shall be compensated by the Contractor for the actual costs to the Owner of engineering, <br />inspection, general supervision, right-of-way costs, permit fees, Overhead expenses, and any other <br />ascertainable direct costs to the Owner that are directly chargeable to the Work and which accrue during <br />the period of such extension. The actual costs do not include charges for final inspection and preparation <br />of the final payment by the Owner. <br />9.5. ADJUSTMENT OF CONTRACT SUM <br />9.5.1 Calculation <br />Except as otherwise expressly provided in these General Conditions, any and all adjustments of Contract <br />Sum shall be determined as follows: <br />1. If the parties are able to agree, the price will be determined by using: <br />a. Unit prices, if the Work items are defined by unit prices; and <br />b. Other prices agreed upon by the Contractor and Owner for Work not defined by unit prices.