My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
Interwest Construction, Inc. 1/13/2026
>
Contracts
>
Capital Contract
>
Capital Construction Contracts and Change Orders
>
Interwest Construction, Inc. 1/13/2026
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
1/13/2026 9:28:40 AM
Creation date
1/13/2026 8:48:36 AM
Metadata
Fields
Template:
Contracts
Contractor's Name
Interwest Construction, Inc.
Approval Date
1/13/2026
Council Approval Date
1/7/2026
Department
Public Works
Department Project Manager
Candice Au-Yeung
Subject / Project Title
36th ST CSO Storage Improvements
Tracking Number
0005068
Total Compensation
$20,955,622.10
Contract Type
Capital Contract
Contract Subtype
Capital Construction Contracts and Change Orders
Retention Period
10 Years Then Transfer to State Archivist
Imported from EPIC
No
Jump to thumbnail
< previous set
next set >
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
1625
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
Download electronic document
View images
View plain text
City of Everett 00 72 00 - 48 00 72 00 - 48 GENERAL CONDITIONS 2. Because of such Delay, the Contractor was forced to suspend or significantly interrupt its performance so that it was on standby or idled, and the Owner required the Contractor to be ready to resume performance on short notice. Extended time of performance of Work, such as extensions caused by changes, inefficiencies, or Extra Work, does not constitute suspension or significant interruption of performance. 3. The Contractor could not and did not use resources, including but not limited to labor, materials and equipment, standing by or idled on this or any other project for any work during the period of delay; 4. The Contractor’s Overhead costs did not materially vary from its usual seasonal Overhead costs during the period of delay; and 5. The Delay did not cause Overabsorbed Overhead in the period in which the delayed Work was completed. 12.4.3.5.2.1 Resources To demonstrate the Contractor could not and did not use resources, including but not limited to labor, materials and equipment from this Project for any other work on this or any other project during the period of delay (12.4.3.5.2.(3)), the Contractor must: a. Affirmatively represent and warrant that it did not perform substitute Work; b. Identify the specific resources that were idled; and c. Show that those resources did not, and could not, work on other contracts or projects during the Delay. 12.4.3.5.2.2 No Material Variations To demonstrate the Contractor’s Overhead costs did not materially vary from its usual seasonal Overhead costs during the period of delay (12.4.3.5.2.(4)), the Contractor must; a. Affirmatively represent and warrant that the completion of the subject Work was extended and that such extension prevented the performance of other work during both the period of delay and the later period of time required to complete the extended Work, b. Disclose the details of Contractor generated billings and Contractor Overhead Costs (as hereinafter defined) throughout the actual project performance. The details of such information should be no less than specific identification of the sources and amounts of revenue on no greater than a monthly basis and specific identification of the types and amounts of Contractor Overhead Costs on no greater than a monthly basis for the actual Project duration. 12.4.3.5.2.3 Overabsorbed Overhead To demonstrate that it did not incur Overabsorbed Overhead in the period following the Delay (12.4.3.5.2.(5)), the Contractor must: a. Affirmatively represent and warrant that completion of the delayed Work prevented the performance of other work; b. Identify the critical resource unavailable for other work due to completion of the delayed Contract; and c. Showing that unavailability of this critical resource precluded the performance of other work. 12.4.4 Inefficiencies 12.4.4.1 Adjustment of Contract Sum To the extent Contractor is entitled to an increase in Contract Sum because of inefficiencies or impaired productivity, then compensation due, if any, shall be calculated as provided in 9.5. ADJUSTMENT OF
The URL can be used to link to this page
Your browser does not support the video tag.