Exhibit A (Scope of Work) <br />Task 13 – Preliminary Design (30%) Plans and Estimate <br />Submittal <br />This task includes preparation of design roll plots, and an opinion of cost estimate <br />based on the preferred alternative roadway improvements. <br />30% Plans <br />Consultant design team will prepare 30% design level roll plots and submit them to the <br />City. The design will be prepared to City CAD standards and to a level of competency <br />presently maintained by practicing professionals in the field of transportation <br />engineering in the Puget Sound Region. <br />It is anticipated that the 30% roll plots will consist of the following design elements: <br />• Alignment and Preliminary ROW <br />• Site Preparation <br />• Channelization <br />• Roadway Improvements <br />• Drainage Improvements <br />• Traffic Signal Improvements <br />• Lighting and ITS Improvements <br />30% Opinion of Cost Estimate <br />Consultant design team will calculate 30% design level quantities and prepare an <br />opinion of construction costs based upon the 30% construction plans and current unit <br />bid prices. A contingency will be included to accommodate additional construction costs <br />not yet specifically identified. Some lump sum and/or square-foot costs will be used for <br />estimating portions of Project costs at this design level. <br />30% QA/QC of Deliverables <br />An internal Consultant quality assurance/quality control review of deliverables will be <br />conducted prior to submittal to the City. <br />Assumptions: <br />• The City will finalize the general geometric layout of the proposed improvements <br />through the review of the 30% submittal. The layout will not be substantially <br />modified in a later design phase. A substantial change in the layout will constitute <br />a change in scope and will allow Consultant to negotiate additional compensation <br />for the change. <br />• City will provide estimate template for the opinion of cost.