PROJECT: City of Everett <br />WFP Phase 2 Capital Upgrades WO No. 3763 <br /> <br />WORK CHANGE DIRECTIVE – No. 04 <br />DATE OF ISSUANCE: February 28, 2025 <br /> <br />You are directed to proceed promptly with the following change (s): <br /> <br />Description: Coating system change on the flocculation basin as required due to high <br />moisture vapor transmission rates through existing concrete in select locations. <br /> <br />Purpose of WCD-04: A coating system change from what was originally specified by the <br />design build team was required in select locations of the flocculation basin due to high <br />moisture vapor transmission rates through the existing concrete. WCD-04 is intended to pay <br />for additional costs associated with the coating system change up to 2/22/25 per the attached <br />documentation. Future costs associated with coating changes in additional locations within <br />the flocculation basin will be included on future work change directives. A future budget <br />reallocation will be executed to formally track funds paying for WCD-04 once the source of <br />said funds, whether they be from City of Everett allowance or IMCO contingency funds, has <br />been determined. <br /> <br />If a claim is made that the above change(s) have affected Contract Price or Contract Times, any <br />claim for a Change Order based thereon will involve one or more of the following methods of <br />determining the effect of the change(s). <br /> <br />Method of determining change Method of determining change <br />In Contract Price: in Contract Times: <br /> <br /> Lump Sum Contractor’s records <br /> <br /> Time and Material Engineer’s records <br /> <br /> Other - Other – N/A <br /> <br /> <br />Estimated increase (decrease) in Contract Price: Estimated increase (decrease) in Contract Times: <br />$127,836.97 Substantial Completion 0 days: <br />If the change involves an increase, the Ready for final payment 0 days: <br />estimated amount is not to be exceeded If the change involves an increase, the <br />estimated without further authorization. times are not to be exceeded without further authorization. <br /> <br /> <br />ACCEPTED: IMCO General Construction AUTHORIZED: City of Everett <br /> <br />By: Date: By: Date: (Authorized Signature) (Authorized Signature) <br />Page 1 of 1 <br />2/28/25