<br />PGSF WMVD Storm and Combined Sewer - Construction Package 2 Erosion and Sedimentation Control <br />Project No. 180162 31 25 00 - 12 <br /> <br />J. At end of each work day, stabilize or cover soil stockpiles or implement other BMPs to <br />prevent discharges to surface waters or conveyance systems leading to surface waters. <br />K. Temporarily stabilize soils at end of shift before holidays and weekends, if needed. <br />Ensure soils are stable during rain events at all times of year. <br />L. Initiate stabilization by no later than end of next work day after construction work in an <br />area has stopped permanently or temporarily. <br />M. Provide permanent erosion control measures on all exposed areas. Do not remove <br />temporary sediment control practices until permanent vegetation or other cover of <br />exposed areas is established. However, do remove all temporary erosion control <br />measures as exposed areas become stabilized, unless doing so conflicts with local <br />requirements. Properly dispose of construction materials and waste, including sediment <br />retained by temporary BMPs. <br />3.02 SEQUENCING AND SCHEDULING <br />A. Submit a TESC Plan for each phase of construction or whenever significant modifications <br />are made to the current TESC Plan or its implementation. <br />1. Contractor shall revise the TESC Plan and its implementation as needed or when <br />requested by the Owner’s Representative based on the actual construction methods, <br />procedures, and observed performances of the provided measures. <br />B. Establish measures identified for implementation prior to commencing any clearing, <br />grading, excavation, or other work that will disturb the ground surface. Surface water <br />drainage and erosion and sediment control devices must be provided before other work <br />commences. <br />C. Perform periodic inspections as required by the TESC Plan. <br />1. The frequency will depend on the time of the year and the construction activities <br />underway at any given time. <br />2. Unless otherwise required, each TESC measure shall be inspected daily and <br />immediately after each rainfall event greater than 0.1 inch of rainfall in 24 hours. <br />3. Prepare TESC Inspection Reports for each inspection and include the report in the <br />TESC file and Site Log Book. <br />4. Submit a record copy of each report to the Owner’s Representative daily. <br />5. Preparing and maintaining an TESC file and Site Log Book. <br />D. Maintain TESC measures for the duration of the contract and/or until restoration of <br />surfaces and ground cover is established to prevent erosion and sedimentation and to <br />ensure stormwater, groundwater and surface flows will be conveyed and controlled in <br />accordance with applicable regulations. <br />E. TESC measures shall be installed, maintained, and removed as indicated in the most <br />recent revision of the approved TESC Plan. <br />1. Any maintenance of facilities which might necessitate unavoidable interruption of <br />operation shall be scheduled during noncritical water quality periods and carried out <br />in a manner approved by the Owner’s Representative.