Laserfiche WebLink
1 <br /> 1 1-09.11A(3)(D) Third Party Caused Delays and Force Majeure <br /> 2 <br /> 3 1-09.11A(3)(D)(1) Caused Solely by Third Parties or Force Majeure <br /> 4 <br /> 5 1-09.11A(3)(D)(1)(a) Adjustment of Contract Sum <br /> 6 <br /> 7 The City and the Contractor shall not be responsible to compensate each other <br /> 8 financially for any Delay solely caused by a third party for whom neither the Contractor <br /> 9 nor the City is responsible, or for any Delay caused solely by earthquake, flood, natural <br /> 10 disasters, acts of war or acts of terrorism. A Delay caused by a utility's failure to provide <br /> 11 service or relocate its lines (despite a timely request for such service or relocation) is an <br /> 12 example of this kind of Delay for which neither the Contractor nor the City is financially <br /> 13 responsible to the other. Mislocated utility lines or utility lines not located are another <br /> 14 example of a Delay for which neither the Contractor nor the City is responsible to the <br /> 15 other. However, the Contractor's failure to request a utility locate or relocation in a <br /> 16 timely way is not, and any resulting Delay would be the responsibility of the Contractor. <br /> 17 Because the Contractor is responsible for ordering materials and equipment, Contractor <br /> 18 shall not be entitled to an adjustment of Contract Time or Contract Sum due to Delays <br /> 19 caused by the lack of materials or equipment. A strike, job action, slowdown, work to <br /> 20 rule, or other job action or labor dispute or problem is not a Delay caused by a third <br /> 21 party. <br /> 22 <br /> 23 1-0-9.11A(3)(D)(1)(b) Adjustment of Contract Time <br /> 24 <br /> 25 The Contractor shall be entitled to an extension of Contract Time for Delays caused <br /> 26 solely by a third party for whom neither the Contractor nor the City is responsible, or for <br /> 27 any Delay caused solely by earthquake, flood, natural disasters, acts of war or acts of <br /> 28 terrorism. Extension of Contract Time shall be determined pursuant to section 1-08.8 <br /> 29 Extensions of Time <br /> 30 <br /> 31 1-09.11A(3)(E) Caused Concurrently by Third Parties and Contractor or Owner <br /> 32 If a Delay is caused concurrently by (a) a third party, earthquake, flood, natural <br /> 33 disasters, acts of war or acts of terrorism and (b) either the Contractor or the City, then <br /> 34 the Contractor or City is only responsible for the amount of Delay it caused in excess of <br /> 35 the Delay caused by the a third party, earthquake, flood, natural disasters, acts of war or <br /> 36 acts of terrorism. <br /> 37 111 <br /> 38 1-09.11A(3)(E)(1) Adjustment of Contract Sum <br /> 39 <br /> 40 The Contractor shall be entitled to an adjustment of Contract Sum for any Delay <br /> 41 concurrently caused by a third party and the City, but only to the extent Contractor <br /> 42 clearly and convincingly demonstrates that the City caused the Delay to be longer than it <br /> 43 would have been had it been caused solely by the third party. <br /> 44 <br /> 45 1-09.11A(3)(E)(2) Adjustment of Contract Time <br /> 46 <br /> 47 The Contractor shall be entitled to an adjustment of Contract Time for any Delay <br /> 48 concurrently caused by a third party and the City, but only to the extent Contractor <br /> 49 clearly and convincingly demonstrates that the City caused the Delay to be longer than it <br /> 50 would have been had it been caused solely by the third party. <br /> 51 <br /> I <br /> RIVERFRONT DEVELOPMENT NORTH WETLAND COMPLEX 88 <br />