I <br /> CITY OF EVERETT PUBLIC WORKS SECTION 01 32 16 <br /> CONSTRUCTION PROGRESS SCHEDULE <br /> SECTION 01 32 16-CONSTRUCTION PROGRESS SCHEDULE <br /> PART 1 -GENERAL <br /> 1 1.1 SECTION INCLUDES <br /> A. Submittals. <br /> B. Format. <br /> C. Review and evaluation. <br /> ' D. Distribution. <br /> 1 1.2 SUBMITTALS <br /> A. Within 10 days after date established in Notice to Proceed, submit draft of proposed complete <br /> bar chart schedule for review. Include written certification that Subcontractors have reviewed <br /> and accepted proposed schedule. <br /> B. Within 5 days after joint review, submit revised Progress Schedule. <br /> C. Submit updated schedules with each Application for Payment and on a weekly basis. <br /> 1 D. Schedule Updates: <br /> 1. Overall percent complete,projected and actual. <br /> 2. Completion progress by listed activity and subactivity, to within five working days prior <br /> to submittal. <br /> 3. Changes in Work scope and activities modified since submittal. <br /> 4. Delays in submittals or resubmittals,deliveries,or Work. <br /> 1 5. Adjusted or modified sequences of Work. <br /> 6. Other identifiable changes. <br /> 7. Revised projections of progress and completion. <br /> E. Narrative Progress Report: <br /> 1. Submit with each weekly submission of Progress Schedule. <br /> 2. Summary of Work completed during the past period between reports. <br /> 3. Work planned during the next period. <br /> 4. Explanation of differences between summary of Work completed and Work planned in <br /> previously submitted report. <br /> 5. Current and anticipated delaying factors and estimated impact on other activities and <br /> completion milestones. <br /> 6. Corrective action taken or proposed. <br /> PSO6 REROUTE 013216- 1 <br /> WO NO.—UP 3583 MAY 2016 <br />