1 <br /> CITY OF EVERETT PUBLIC WORKS DOCUMENT 00 72 13 i <br /> SPECIAL PROVISIONS GENERAL CONDITIONS <br /> Time arising out of, or related to,work it performs prior to receipt of the Notice to Proceed. The I <br /> Owner may issue partial Notices to Proceed. <br /> 5.2 Contract Time I <br /> A. General <br /> 1. TIME IS OF THE ESSENCE IN PERFORMING THE CONTRACT. <br /> a. Failure to complete the Project within the contractually specified time may affect other <br /> Projects and Owner activities. Contract Time starts upon the later of the issuance of the <br /> Notice to Proceed or a date specified in the Notice to Proceed. The Contractor shall <br /> promptly start the Work as soon as possible after the date of the Notice to Proceed and <br /> shall prosecute the Work so that the various portions of the Project shall be completed <br /> in accordance with the Contract Time period. Contractor shall perform its work at such <br /> times and in such ways that the Work is not damaged by weather such as wind, rain, or <br /> snow. Contractor shall correct or repair at its sole expense any Work damaged by <br /> weather, irrespective of whether such damage is covered by insurance. No portions of <br /> the Work where acceptable quality will be affected shall be constructed while <br /> unfavorable conditions exist. By bidding on the Project and executing a Contract to <br /> perform the Work, Contractor agrees the contractually required completion dates are <br /> feasible,reasonable, and achievable for the Contract Sum. Contractor represents that it <br /> has considered all factors relevant to its price and achieving the Completion Dates, <br /> including, but not limited to, weather, Site access, labor conditions and the availability <br /> of materials, supplies and Equipment. Compliance with ARTICLE 10. NOTICE TO <br /> OWNER, ARTICLE 12. CONTRACT CLAIMS, and 5.2.B. Construction <br /> Schedule are conditions precedent to a request for, consideration of, and grant of, any <br /> extension of Contract Time. Failure to request a time extension in the manner and in <br /> the time required by this section, and the Specifications referred to herein, constitutes a <br /> waiver by the Contractor of any and all entitlement to an extension of time and any <br /> adjustment of Contract Sum arising out,or related to,such Delay. <br /> B. Construction Schedule t <br /> 1. General <br /> a. Contractor shall submit, update and maintain schedules as required by the Contract <br /> Documents. <br /> b. The Contractor shall provide sufficient material, equipment, and labor to meet the <br /> interim. milestones, Substantial Completion, Physical Completion and Completion <br /> Dates provided by the Contract Documents. The Owner allocates its resources to a <br /> Contract based on the total time allowed in the Contract. The Contractor may submit a <br /> schedule indicating Completion Date earlier than the end of Contract Time, but Owner <br /> cannot guarantee its resources will be available to meet such schedule. Owner shall not 111pay or be liable for any additional compensation if the Contractor is not able to meet a <br /> schedule that indicates a Completion Date earlier than the end of Contract Time. <br /> c. Failure to schedule Owner furnished or installed materials and Equipment for <br /> installation on or after its planned arrival pursuant to the Owner's contract with the <br /> supplier or failure to Notify the Owner of tasks dependent upon the fact or date of <br /> arrival of such Owner furnished materials and Equipment, constitute a waiver by <br /> Contractor of any Contract Claim arising out of or related to the timeliness of the <br /> furnishing or installation of such material and Equipment. All schedules must allow for <br /> timely incorporation of any other's work under separate contract with Owner and for <br /> PSO6 REROUTE 007213 -22 <br /> WO NO.—UP3583 MAY 2016 <br /> 1 <br />