Laserfiche WebLink
I <br /> POLICE HQ— MASONRY CLEANING AND REPAIR APRIL 15, 2016 <br /> 111 <br /> The Owner and the Contractor shall not be responsible to compensate each other financially for <br /> any Delay solely caused by a third party for whom neither the Contractor nor the Owner is <br /> responsible, or for any Delay caused solely by earthquake, flood, natural disasters, acts of war or <br /> acts of terrorism. A Delay caused by a utility's failure to provide service or relocate its lines <br /> (despite a timely request for such service or relocation)is an example of this kind of Delay for <br /> which neither the Contractor nor the Owner is financially responsible to the other. Mislocated <br /> utility lines or utility lines not located are another example of a Delay for which neither the <br /> Contractor nor the Owner is responsible to the other. However,the Contractor's failure to request <br /> a utility locate or relocation in a timely way is not,and any resulting Delay would be the <br /> responsibility of the Contractor. Because the Contractor is responsible for ordering materials and <br /> Equipment, Contractor shall not be entitled to an adjustment of Contract Time or Contract Sum <br /> due to Delays caused by the lack of materials or Equipment. A strike,job action, slowdown, <br /> work to rule,or other job action or labor dispute or problem is not a Delay caused by a third party <br /> for the purposes of section 12.4.3 Delays. <br /> 12.4.3.4.1.2 Adjustment of Contract Time <br /> The Contractor shall be entitled to an extension of Contract Time for Delays caused solely by a <br /> third party for whom neither the Contractor nor the Owner is responsible,or for any Delay caused <br /> solely by earthquake,flood,natural disasters,acts of war or acts of terrorism. Extension of <br /> Contract Time shall be determined pursuant to 5.2.2.2 Extensions of Contract Time. <br /> 12.4.3.4.2 Caused Concurrently by Third Parties and Contractor or Owner <br /> If a Delay is caused concurrently by(a)a third party, earthquake, flood,natural disasters, acts of war <br /> or acts of terrorism and(b)either the Contractor or the Owner,then the Contractor or Owner is only <br /> responsible for the amount of Delay it caused in excess of the Delay caused by the a third party, <br /> earthquake, flood,natural disasters,acts of war or acts of terrorism. <br /> 12.4.3.4.2.1 Adjustment of Contract Sum <br /> The Contractor shall be entitled to an adjustment of Contract Sum for any Delay concurrently <br /> caused by a third party and the Owner,but only to the extent Contractor clearly and convincingly I <br /> demonstrates that the Owner caused the Delay to be longer than it would have been had it been <br /> caused solely by the third party. <br /> 12.4.3.4.2.2 Adjustment of Contract Time I <br /> The Contractor shall be entitled to an adjustment of Contract Time for any Delay concurrently <br /> caused by a third party and the Owner,but only to the extent Contractor clearly and convincingly <br /> demonstrates that the Owner caused the Delay to be longer than it would have been had it been I <br /> caused solely by the third party. <br /> 12.4.3.5 Extended or Unabsorbed Overhead <br /> 12.4.3.5.1 General <br /> To present a request for additional compensation for Extended or Unabsorbed Overhead,the <br /> Contractor has the burden of keeping and maintaining accurate documentation to support any such <br /> claim. If the Contractor fails to provide or keep adequate financial data for an accurate and fair <br /> Eichleay calculation, Contractor waives and releases any claim for Unabsorbed or Extended <br /> Overhead. In presenting any claim under this section of the Contract,the Contractor agrees to provide <br /> to the Owner any and all financial data needed by the Owner,or its representative,to review, <br /> substantiate and evaluate any claim for Extended and/or Unabsorbed Home Office Overhead. Failure <br /> to provide the requested information shall constitute waiver by the Contractor. <br /> If Contractor is entitled to an adjustment of Contract Sum for Unabsorbed or Extended Overhead,it I <br /> shall be calculated as provided in 9.5.3.Unabsorbed and Extended Overhead. 9.5.3 <br /> Unabsorbed and Extended Overhead <br /> GENERAL CONDITIONS 00 7200-46 <br /> 1 <br />