I <br /> POLICE HQ— MASONRY CLEANING AND REPAIR APRIL 15, 2016 <br /> 9. MEASUREMENT AND PAYMENT <br /> 9.1. PAYMENTS TO CONTRACTOR 1 <br /> 9.1.1. Schedule of Values <br /> The Contractor shall submit a Schedule of Values at least fifteen(15)days prior to submitting its first 1 <br /> Application for Payment. If the Project contains Unit Price Work, in whole or in part,then the Schedule <br /> of Values for that portion of the Work shall also be based on unit prices. If the Bid form calls for a lump <br /> sum price,in whole or in part,then the Schedule of Values shall: reasonably allocate the Contract Sum <br /> among the various portions of the Work;be complete;be organized to include detailed breakdown of each <br /> major unit of the Work;be organized to correspond to Contractor's schedule;break down the Contract <br /> Sum showing the value assigned to each part of the Work; include an allowance for profit and Overhead; <br /> include Unit Price Work,if and to the extent indicated on the Bid form;be so organized as to facilitate <br /> assessment of work and payment of Subcontractors;and be balanced. To the greatest extent possible,the <br /> breakdown shall use the same tasks or units as the Contractor's schedule. Contractor shall provide <br /> documentation substantiating the cost allocation if asked by the Owner's Representative. Upon <br /> acceptance of the Schedule of Values by the Owner's Representative, it shall be used as a basis for all <br /> requests for payment. <br /> 9.1.2. Progress Payments I <br /> 9.1.2.1 Payment Request Procedures: <br /> By the tenth day of each month, or by schedule mutually agreed upon in writing by the Contractor and <br /> Owner's Representative,the Contractor shall submit to the Owner's Representative a partial payment <br /> estimate filled out and signed by the Contractor covering acceptable Work performed during the previous <br /> month, or since the last partial payment estimate was submitted. Contractor's submission of a progress <br /> pay estimate constitutes a material representation by the Contractor that it performed all of the Work111 <br /> described in the progress pay estimate during the relevant time period in a workmanlike manner and that <br /> the materials for which payment is requested reasonably conform to the Specifications and are either on <br /> the job Site or have been installed. If requested by the Owner's Representative, the Contractor shall <br /> provide such additional data as may be reasonably required to support the payment estimate. Such data <br /> may include satisfactory evidence of payment for Equipment,materials and labor including payments to <br /> Subcontractors and Suppliers. Certified invoices by the Suppliers shall accompany a request for payment <br /> for delivered Equipment and material. Such Equipment and material shall be suitably and safely stored at <br /> the Site of the Work. Payment requests shall summarize accepted operating and maintenance material <br /> with request for Equipment payment. A progress payment is preliminary only. By making a progress <br /> payment, the Owner does not waive or release its right,nor is it estopped from asserting, that previous <br /> progress payments were not earned or were in error,whether in whole or in part. <br /> 9.1.2.2 Review Procedures: <br /> The Owner's Representative will review the estimate and either indicate in writing to the Owner his or <br /> her concurrence with the estimate and his or her recommendation that payment be made,or indicate in <br /> writing to the Contractor his or her reasons for not concurring with the estimate. If the Owner's <br /> Representative recommends payment and the Owner concurs, the Owner will pay the Contractor a <br /> progress payment on the basis of the approved partial payment estimate, less retainage and any amounts <br /> the Owner may withhold pursuant to Contract or law. The recommendation of the Owner's <br /> Representative is not conclusive, final or binding upon the Owner. <br /> In the event the Owner's Representative does not concur with the estimate,the Contractor may make the <br /> changes necessary to obtain the Owner's Representative's concurrence and resubmit the partial payment <br /> estimate, or submit the original progress payment estimate directly to the Owner, indicating in writing its <br /> reasons for refusing to make the changes necessary to obtain concurrence. <br /> GENERAL CONDITIONS 00 7200 -30 <br /> I <br />