Project: Riverfront Development Sanitary Sewer <br /> Lift Station Improvements <br /> Change Order No.6 <br /> Change Order Effective Date: July 18, 2016 <br /> cost credit to the City of Everett to account for being able to accomplish this work during normal <br /> business hours. <br /> Schedule "A" Bid Item #211 —Lift Station 33-Geotextile Liner Repair. The contractor damaged <br /> the landfill geotextile liner during excavation for the construction of lift station 33. The geotextile liner <br /> was not shown on the plans and the Contract did not provide a method of payment for the Contractor <br /> to repair the liner. This bid item is being added to account for costs required to pay for the repair of <br /> the geotextile liner. <br /> Schedule "A" Bid Item #22 —Force Account. <br /> Schedule "B" Bid Item # 104—Force Account. <br /> These bid items have overrun their plan quantities and are being modified to account and pay for costs <br /> incurred by quantity overruns plus future increases to these bid items. <br /> This Change Order# 6 results in an increase to the Contract price of$127,940.00. <br /> Exhibit C--Contract Time <br /> Fifteen (15)working days are added to the Contract time to account for the time to install Lift <br /> Station 43 electrical work for PUD. An additional ten (10)working days are added to the <br /> Contract time to account for additional electrical and piping work paid for under force account <br /> bid items. A total of 25 working days are being added to the Contract by change order# 6. <br /> Page 5 of 5 <br />