Laserfiche WebLink
AOS BROS. CONSTRUCTION,INC. <br /> CONSTRUCTION MANAGEMENT, PLAN <br /> THE HOEING 40-41 777 TESTING FACILITY <br /> The completion schedules for the utilitiea are as follows: <br /> Sanitary Sewer - (5) calendar days• <br /> Storm Sewer - (7) calendar days. <br /> Water System - (8) calendar days. <br /> Utilidor - (7) calendar days. <br /> 6 1 FINEOR7IDE <br /> As the utilities are installed through the site, <br /> rock9 ephalt pavinge concrete flat8work ndfsubgrade for <br /> landscaping. • <br /> The concrete work will ba completed in (10) calendar daand the <br /> overall finegrade land ecle nup twill be oomplet d in ()I calendar <br /> days. <br /> � BECURITT lENCE GWIRDRI�IL 6TRIPINa 1186ELSTOPB AND BIa1111aE <br /> The final phase of the project will include the permanent <br /> security fence throughWheelsto stand8applicnbleieignnge <br /> parkinq lot etriping, p <br /> as outlined in the construction documents. <br /> This work will be completed in (8) calendar days. <br /> NOTEB <br /> A� � a completion t rgettdate ofnDecember� 18, 1992 lfor the worklae <br /> deecribed above. <br /> g, ) The attached echedule reflects time duration in days only, <br /> actual date sequence will be made avnilable upon receipt of <br /> the outstanding permit and contract. <br /> Page 4 <br />