Laserfiche WebLink
5 • Temporary work platform (Item 21) <br /> Further descriptions of the these differences are summarized below: <br /> Mobilization (Item 1) <br /> The engineer's opinion of probable cost assumed mobilization project costs to equal <br /> approximately five (5) percent of the subtotal construction cost. Mobilization costs typically <br /> include items such as procuring the project field office, preparation of shop drawing submittals, <br /> mobilization of equipment, B&O taxes, and other administrative costs that occur during the <br /> startup of the project. The mobilization costs found in the three-bid schedules ranged from a low <br /> of 7.1% to a high of 12.3% of the subtotal cost for other bid items. The higher percentages used <br /> by the bidders in the mobilization bid item becomes even more significant due to the larger <br /> subtotal of the bid prices reflected in the bid proposals resulting from some of the other bid <br /> items. For example, the higher mobilization percentage used in the low bidder's (Tri-State) <br /> proposal for Bid Schedule C (7.1%) as compared to that used in the engineer's opinion of <br /> probable cost (5%) results in an additional cost of$772,468. <br /> Elevated Walkway— Pipelines No. 2 & 3/Pipeline No. 4 (Items 26, 27 and 64) <br /> The engineer's opinion of probable cost for the elevated walkways was based on a unit cost price <br /> of $70 for the walkway between Pipelines 2 and 3 (bid Item 26) and $40/lineal foot for the <br /> Pipeline 4 walkway (bid items 27 and 64) compared to the low bidder's unit cost of$135/lineal <br /> foot for each item. This represents a total cost difference of $1,057,600. Several factors may <br /> account for this cost difference including under estimating the crew time required, the restricted <br /> access requirements and the volatility in the steel price industry (steel beams and walkway <br /> grating). It also appears that the low bidder did not differentiate between the cost of the Pipeline <br /> 2/3 walkway (involving a 5 ft wide grating and two W12 x 58 longitudinal steel beams), and the <br /> Pipeline 4 walkway(involving only a 3-ft 4-inch walkway and no longitudinal beams) <br /> Install/ Remove Temporary Work Platform (Item 21) <br /> As described previously, the engineer's opinion of probable cost was based on an assumed <br /> construction access method involving a temporary work platform supported directly on the <br /> permanent steel piles. This approach minimizes the number of temporary pile bents required for <br /> construction access. The permanent pile bents are capable of supporting a 150-ton crane load <br /> plus the working platform weight. Responsibility for the design of the temporary work platform <br /> remains with the Contractor, based on their construction plan. The three bidders that proposed <br /> on the Phase 6 work developed three different concepts for the temporary work platform, <br /> resulting in costs ranging from $4.22 to $7.10 million. This price is substantially higher than the <br /> $1.65 million shown in the engineer's opinion of probable cost. This bid item alone accounts for <br /> a difference of$5,049,136 between the engineer's opinion of probable cost and the low bidder's <br /> price. <br /> There are several factors directly impacting the cost of the temporary work platform that appear <br /> to have contributed to this significant cost difference, as described below: <br /> 1. Restrictions on timing of in-water activities: During the original design work no <br /> winter timing restrictions were anticipated for the construction work. However, near <br /> the end of the design phase, the Corps of Engineer's Nationwide-permit imposed <br /> MWH—TECHNICAL MEMORANDUM Page 3 TRANSMISSION LINES 2&3—PHASE 6&7 <br /> APRIL 22,2005 ASSESSMENT OF BIDDER'S PRICE PROPOSALS <br /> 15 <br />