rrun uare: 9/40/Lvv0 city of tverett- Public Works Department Cutoff Date: 4/15/2005
<br /> Time: 11:38 AM Contract Estimate Voucher
<br /> Project: 175 For Work Order#3189 Contractor: R.L.ALIA COMPANY
<br /> N. END BASEMENT FLOOD Estimate#9 107 WILLIAMS AVE S
<br /> REDUCTION"F"
<br /> WO 3189 BID:$1,724,130.00 RENTON WA 98055
<br /> TOTAL BID:$1,724,130,00 _
<br /> Unit Plan Total Previous Present Total Previous Present
<br /> Item 4 Description Units Price Quantity Quantity Quantity Quantity Amount Amount Amount
<br /> 0001 Mobilization LS 129,000.00 1.00 1.0000 1.0000 0.0000 129,000.00 129,000.00 0.00
<br /> 0002 Trench excavation safety system LS 10,000.00 1.00 1.0000 1.0000 0.0000 10,000.00 10,000.00 0.00
<br /> 0003 Surveying LS 5,000.00 1.00 1.0000 1.0000 0.0000 5,000.00 5,000.00 0.00
<br /> V-'0004 Traffic control labor HR 35.00 2,000.00 1,412.5000 1,412.5000 0.0000 49,437.50 49,437.50 0.00
<br /> 0005 Maintenance&protec tion of traffic control LS 2,000.00 1.00 1,0000 1.0000 0.0000 2,000.00 2,000.00 0.00
<br /> 0006 Sawcutting pavement LF 3.00 5,100.00 2,549.0000 2,549.0000 0.0000 7,647.00 7,647.00 0.00
<br /> 0007 Manhole,type 1,48"diam. EA 5,000.00 10.00 12.0000 12.0000 0.0000 60,000.00 60,000.00 0.00
<br /> 0008 Manhole,type 1,54"dlam. EA 6,000.00 3.00 3.0000 3.0000 0.0000 18,000.00 18,000.00 0.00
<br /> 0009 Drop manhole connection EA 3,000.00 13.00 15.0000 15.0000 0.0000 45,000.00 45,000.00 0.00
<br /> 0010 Tree removal LS 200.00 1.00 0.0000 0.0000 0.0000 0.00 0,00 0.00
<br /> 0011 Side sewer connection EA 500.00 220.00 218.5000 218,5000 0.0000 109,250.00 109,250.00 0,00.
<br /> 0012 Combined sewer pipe,8"DI,PVC,SDR 35 LF 119.00 290.00 293.0000 293.0000 0.0000 34,867,00 34,867.00 0.00
<br /> 0013 Combined sewer pipe,10"DI,PVC,SDR35 LF 120.00 680.00 680.0000 680.0000 0.0000 81,600.00 81,600.00 0.00
<br /> 0014 Combined sewer pipe,12"DI,PVC,SDR 35 LF 122.00 1,920.00 1,946.0000 1,946.0000 0.0000 237,412.00 237,412.00 0.00
<br /> 0015 Combined sewer pipe,18"Dt,PVC,SDR 35 LF 130.00 500.00 500.0000 500.0000 0.0000 65,000.00 65,000.00 0.00
<br /> 0016 Combined sewer pipe,8"DI,PVC,SDR 25 LF 121.00 700.00 698.0000 698.0000 0.0000 84,458.00 84,458.00 0,00
<br /> ( 0017 Combined sewer pipe,10"DI,PVC,SDR 25 LF 123.00 730.00 729.0000 729.0000 0.0000 89,667.00 89,667.00 0.00
<br /> 0018 Combined dewer pipe,12"DI,PVC,SDR 25 LF 125.00 960.00 960.0000 960.0000 0.0000 120,000:00 120,000.00 0.00
<br /> 0019 Combined sewer pipe,12"DI HDPE LF 130.00 480.00 0.0000 0.0000 0.0000 0.00 0.00 0,00
<br /> 0020 Storm drain connec tion to existing EA 1,000.00 17.00 21.0000 21.0000 0.0000 21,000.00 21,000.00 0.00
<br /> 0021 Storm drain pipe,8"DI LF 30.00 250.00 380.0000 380.0000 0.0000 11,400.00 11,400,00 0.00
<br /> 0022 Catch basin,type B with gas trap EA 1,000.00 11.00 14.0000 14.0000 0.0000 14,000.00 14,000.00 0.00
<br /> 0023 Foundation material,Class A TN 10.00 500.00 335.0600 335.0600 0.0000 3,350.60 3,350.60 0.00
<br /> 0024 Gravel borrow TN 8.00 25,000.00 11,881.2100 11,881.2100 0,0000 95,049,68 95,049.68 0.00
<br /> 0025 Crushed surfacing top course TN 15.00 2,900.00 4,668.4000 4,640.7200 27.6800 70,026.00 69,610.80 415.20
<br /> 0026 Control density fill CY 100.00 50.00. 1.5000 1.5000 0.0000 150.00 150.00 0.00
<br /> 0027 Topsoil Type A CY 40.00 200.00 147.0000 114.0000 33.0000 5,880.00 4,560.00 1,320.00
<br /> Md