SMART CARD PROJECT CHANGES <br /> 5 <br /> IBI Change Order History <br /> DATE PURPOSE <br /> 1-4. 3/00 — 7/02 Occurred before Everett was a partner in the project <br /> 5. 5/03 Council action; Provide Contract Implementation <br /> Services for Phase IV, system design and implementation. <br /> 6. 6/04 Changed scope to provide additional technical assistance for <br /> the Regional Tech Manager and increased budget by $84,000 <br /> (2.88% ET share = $2,419.20). <br /> 7. 7/04 Revise contract period of performance. No direct cost. <br /> 8. 11/04 Additional tasks to cover development and ongoing <br /> administration costs Sept 04 — February 05. Develop user- <br /> friendly reports and produce Traceability Matrix. Increase <br /> budget by $90,700 (2.88% ET share = $2,612.16) <br /> 9. 4/05 Reallocate previously approved funds for future tasks to <br /> current tasks. Total fund shift $33,855 with no direct cost to <br /> ET. <br /> 31 <br /> Smart Card Ratifying Changes Summary/1.0-12-05 Agenda Item Page 2 of 4 <br />