MSA <br /> EXHIBIT C <br /> TIME SCHEDULE OF COMPLETION <br /> City of Everett <br /> Replacement of Reservoir 2 <br /> Work Order#UP3658 <br /> Phase 1 - Preliminary Design <br /> PRELIMINARY ESTIMATED SCHEDULE <br /> MSA shall begin work immediately upon receipt of Notice to Proceed from the City and proceed <br /> according to the preliminary estimated schedule presented below. However, the schedule may <br /> change due to factors beyond MSA's control, such as additional time required for permitting, <br /> public outreach, etc. <br /> Preliminary Design Tasks Estimated Completion <br /> Notice to Proceed February 3, 2017 <br /> Task 101 —Project Management February—September 2017 <br /> Task 102—Project Coordination February—September 2017 <br /> Task 201 —Data Collection and Utility Coordination February—March 2017 <br /> Task 202— Site Reconnaissance and Geotechnical Coordination February—April 2017 <br /> Task 203—Surveying and Mapping February—March 2017 <br /> Task 204—Alternatives Evaluation and Conceptual Design April—July 2017 <br /> Task 205 —Preliminary Design July—September 2017 <br /> Task 206—DOH Project Report July—September 2017 <br /> Task 207—Public Outreach and Permitting Support As Requested by City <br /> Task 301 —Unanticipated Supplemental Services As Requested by City <br /> Estimated Final Design, Bidding and Construction Estimated Completion <br /> Tasks* p <br /> Final Design September 2017—May 2018 <br /> Bidding May—June 2018 <br /> Construction July 2018—December 2019 <br /> *Final design, bidding and construction schedule contingent upon results of preliminary design <br /> phase and final scope of the proposed project improvements. <br /> City of Everett MURRAY,SMITH&ASSOCIATES,INC. Replacement of Reservoir 2 <br /> January 12,2017 Engineers/Planners Page 1 <br />