Laserfiche WebLink
Schedule and Sequencing � <br /> �r� <br /> 5) Anticipated Timeframe/Schedule <br /> Event Date <br /> Construction Start April 2012 <br /> System Startup August 2012 <br /> Substantial Completior October 2012 <br /> 6) Are there any other projects or phases associated with this project? <br /> • Phase 2 interim action to prevent TCE contaminated groundwater from discharging <br /> to Powder Mill Creek off of Boeing property (CoE Lot 9, Intermec, CRISTA) <br /> • Phase 2 investigation/pilot studies in 2012 <br /> • Phase 2 conceptual design and work plan in 2013 <br /> • Construction/irr�plementation of Phase 2 in 2014 <br />