• <br /> Change Order Cover Sheet/For Internal City Use Only <br /> CONTRACT TIME <br /> Original Contract Duration Working Days ❑ Calendar Days ® 90 <br /> Date of Notice to Proceed 9/5/2006 <br /> Cumulative adjustment to duration by prior Change Orders 90 <br /> Adjustment to duration by this Change Order 45 <br /> New Contract Duration (including this Change Order) 225 <br /> EXPLANATION/JUSTIFICATION <br /> Construction of Garfield Park Improvements is substantially complete. Since Council approval of Change Order#2 on January <br /> 31, 2007, the following has occurred on the project: <br /> 1)When the parking lot on 24th Street was stripped and the subgrade exposed, further abandoned drain lines were <br /> discovered. The drain lines were excavated and suitable materials were imported and compacted. The cost of this work is <br /> $3,956.28 plus Washington State sales tax. <br /> 2)To assist,with surface water drainage, an ADA-accessible ramp was cut in the curb at the north end of the parking lot on <br /> State Street. An additional ADA parking stall was added adjacent to the new ramp. The cost of this work is $2,904.16 plus <br /> Washington State sales tax. <br /> Total cost of this change is $6,860.44 plus Washington State sales tax. Contract time has been extended due to additional <br /> work and weather conditions in February and March, causing delays in completion. <br /> CityStaff Contact: Jonna Hauser <br /> Date: 4/2/2007 <br />