Cs� <br /> Work Plan for Project <br /> Task/Activity <br /> Person/Team Responsible Completion Date Duration <br /> Finalize Work Plan with Contractor—Management from Bob Jackson July 15 3 weeks <br /> EarthCorps, our trail builders, will take measurements and <br /> set construction marking stakes on June 21. From that <br /> survey a final scope of work will be refined. This will spell <br /> out how much of the site preparation work can be done by <br /> neighborhood volunteers prior to the arrival of an <br /> EarthCorps crew. This plan will set the final budget within <br /> the guidelines of expected income. <br /> Site preparation—Trail grubbing and plant salvaging will Friends of Forgotten Creek September 30, 2007 10 weeks <br /> be accomplished. work parties/Bob Jackson <br /> Trail construction—Approximately 350 feet of sloped, EarthCorps crew/Jammie October 31, 2007 10 days <br /> switchbacking trail including 24 box steps and one ten-foot Stauffer, EarthCorps Project <br /> puncheon bridge will be built. Manager <br /> Trail surfacing—one to two inches of 5/8 inch, top course Friends of Forgotten Creek November 10, 2007 1 day <br /> gravel will be spread on trail. work parties/Bob Jackson <br /> In preliminary talks with EarthCorps, it is our expectation that the project can be done sometime in October. This is dependent on <br /> their work schedule and crew availability, so an exact date is yet to be determined. <br /> 5 <br />