Laserfiche WebLink
Change Order Cover Sheet/For Internal City Use Only 7 <br /> CONTRACT TIME <br /> Original Contract Duration Working Days ❑ Calendar Days ® 100 <br /> Date of Notice to Proceed 12/12/07 <br /> Cumulative adjustment to duration by prior Change Orders 0 <br /> Adjustment to duration by this Change Order 27 <br /> New Contract Duration (including this Change Order) 127 <br /> EXPLANATION/JUSTIFICATION <br /> Change Order#1 has been negotiated on a time and materials basis to remedy structurally unsuitable soils and an artesian <br /> spring discovered within the skate park footprint. The contractor has removed the unsuitable soil and has imported quarry rock <br /> and crushed stone to provide structural stability and a drainage course to redirect the artesian spring. Three test pits dug by <br /> staff prior to construction on the one acre site did not encounter any structurally unsuitable soils. <br /> CityStaff Contact: Henry Schroder <br /> Date 3-28-08 <br /> 20 <br />