Change Order Cover Sheet/For Internal City Use Only <br /> 7 <br /> CONTRACT TIME <br /> Original Contract Duration Working Days ❑ Calendar Days ® 210 Days <br /> Date of Notice to Proceed 7/6/09 <br /> Cumulative adjustment to duration by prior Change Orders 30 <br /> Adjustment to duration by this Change Order 0 <br /> New Contract Duration (including this Change Order) 240 Days <br /> EXPLANATION/JUSTIFICATION <br /> Change Order No.three contains a list of additional work that is required to: <br /> (a) Correct unforseen conditions in the existing site. <br /> (b) Correct oversights in the plans and specifications <br /> (c) Improve the quality of appearance and performance of the site and building. <br /> (d) Correct extensive underlying structural damages due to moisture intrusion and <br /> pest damage. <br /> • <br /> CityStaff Contact: Ruben Sanchez, 425-257-8896 <br /> Date 1/7/10 <br /> 21 <br />