BID TABULATION
<br /> Riverfront Surcharge Phase 3 Schedule B
<br /> W.O.#RD3316
<br /> Date 5/19/2010
<br /> Prepared By:William Barrett
<br /> For:Tim Marks,Project Engineer ENGINEER'S ESTIMATE KLB Construction Hos Bros.Construction Northwest Construction Scarsella Bros.,Inc
<br /> ITEM UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL
<br /> - -
<br /> # ITEM DESCRIPTION UNIT QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE ,._ AMOUNT PRICE AMOUNT PRICE AMOUNT
<br /> 1 Mobilization LS 1 $45,000.00 $45,000.00 $31,600.00 $31,600.00 $6,488.00 $6,488.00 $5,000.00 $5,000.00 $1.00 $1.00
<br /> 2 Construction Survey LS 1 $12,000.00 $12,000.00 $1,500.00 $1,500.00 $5,250.00 $5,250.00. $2,500.00 $2,500.00 $1,000.00 $1,000.00.
<br /> 3 Site Demolition&Salvage LS I $23,100.00 $23,100.00: $2,500.00 $2,500.00 $8,703:66 $8,703.66 $7,800.00 $7,800.00 $6,000.00 $6,000.00
<br /> 4 Temporary Erosion& LS 1 $20,000.00 $20,000.00 $7,500.00 $7,500.00 $3,028.18 $3,028.18 $38,000.00 $38,000.00- $7,500.00 $7,500.00
<br /> Sedimentation Control
<br /> 5 Hydroseeding Acre 1.5 $700.00 $1,050.00 $630.00 $945.00 $656.25 $984.38 $610.00 $915.00 $660.00 S990.00
<br /> 6 Excavate uncontaminated soil, CY 8,000 $5.00 $40,000.00 $6.00 $48,000.00 $4.70 $37,600.00 $4.40 $35,200.00 $6.20 $49,600.00
<br /> stockpile,move,place and compact
<br /> on-site
<br /> 7 Excavate,transport,and off-site Ton 6,000 $70.00 $420,000.00 $46.65 $279,900.00 $50.98 $305,880.00 $40.00 $240,000.00 $50.50 $303,000.00
<br /> disposal of contaminated soil
<br /> 8 Contaminated dewatering LS 1 $5,000.00 $5,000.00 $10,000.00 $10,000.00 $3,675.00 $3,675.00 $29,000.00 $29,000.00 $5,000.00 $5,000.00
<br /> Discharge
<br /> 9 Soil Sampling&Testing HR 100 $200.00 $20,000.00 $1.00 $100.00 $140.58 $14,058.00 $88.00 $8,800.00 $130.00 $13,000.00
<br /> Coordination
<br /> 10 Underground Storage Tank FA 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $10,000.00
<br /> 1-- Removal&Closure
<br /> II ORC Building LB 1,000 $10.00 $10,000.00 $16.00 $16,000.00 $13.53 $13,530.00 $12.00 $12,000.00 $13.25 $13,250.00
<br /> 12 Monitoring Wells/Gas Probes, EA 2 $500.00 $1,000.00 $350.00 $700.00 $525.00 $1,050.00 $700.00 $1,400.00 $1,750.00 $3,500.00
<br /> Adjust Grade
<br /> 13 Monitoring Wells/Gas Probes, EA 2 $500.00 $1,000.00 $2,500.00 $5,000.00 $1,050.00 $2,100.00 $1,200.00 $2,400.00 $1,000.00 $2,000.00
<br /> Decommision
<br /> 14 Settlement Plates EA 4 $700.00 $2,800.00 $350.00 $1,400.00 $403.75 $1,615.00. $250.00 $1,000.00 $600.00 $2,400.00