Laserfiche WebLink
i <br /> Project: <br /> Change Order No. <br /> Change Order Effective Date: <br /> By Date: 9//r77 <br /> Officer <br /> Exhibit A—Description of Changed Work <br /> The total quantity of material identified in bid item B7 that was excavated, tested and found to be <br /> contaminated, transported and disposed of offsite increased from 6000 tons to 10,306.32 tons. All <br /> contaminated material was required to be removed from the limits of the project site. This resulted in a <br /> quantity over-run of bid item B7. This change order will correct this over-run by increasing the Final <br /> Estimated Quantity to 10,306.32 tons and increasing the Final Estimated Amount to $480,789.83. The <br /> bid price for this unit rate, $46.65 per ton, remains the same. <br /> 4 <br /> Page 3 of 3 <br />