BID SUMMARY
<br /> Sewer System Replacement and Capacity Improvements "L" -North Area
<br /> W.O.#UP3398-A
<br /> Date Nov.2,2010
<br /> For.Dave Voigt,Project Engineer
<br /> Bidder Name: Bidder Totals: Comment •
<br /> ENGINEER'S ESTIMATE Base Bid $5,050,000.00
<br /> Alternate Bid $4,975,000.17
<br /> Shoreline Construction Base Bid $3,424,840.30 Low Bidder
<br /> Alternate Bid $3,385,340.30
<br /> •
<br /> SCI Infrastructure Base Bid $3,513,497.90
<br /> Alternate Bid $3,512,510.40
<br /> HOS Brothers Base Bid $3,596,000.00
<br /> Alternate Bid $3,574,275.00
<br /> KLB Construction Base Bid $3,791,294.90
<br /> Alternate Bid $3,771,544.90
<br /> MidMountain Contractors Base Bid $4,177,444.00
<br /> Alternate Bid $4,157,694.00
<br /> Rodarte Construction,Inc Base Bid $4,193,783.00
<br /> Alternate Bid $4,179,958.00
<br /> Titan Earthworks,LLC Base Bid $4,206,754.65
<br /> Alternate Bid $4,181,079.65
<br /> Northwest Construction,Inc Base Bid $3,883,750.00 $4,243,200.00 Total Bid Amounts do
<br /> Alternate Bid $3,864,000.00 $4,223,450.00 not equal sum of bid
<br /> New West Development Base Bid $4,360,851.50
<br /> Alternate Bid $4,339,126.50
<br /> Buno Construction Base Bid $4,376,258.00
<br /> Alternate Bid $4,356,508.00
<br /> Plats Plus,Inc. Base Bid $4,497,715.50 Corrected error for bid
<br /> Alternate Bid $4,472,040.50 item#30
<br /> R.L.Alia Company Base Bid $4,596,171.50
<br /> Alternate Bid $4,576,421.50
<br /> Jennings Northwest,LLC Base Bid $4,610,414.00
<br /> Alternate Bid $4,586,714.00
<br /> Interwest Construction,Inc. Base Bid $4,789,624.50
<br /> Alternate Bid $4,769,874.50
<br /> SRV Construction Base Bid $5,309,486.70
<br /> Alternate Bid $5,273,936.70