Laserfiche WebLink
Project File M&N#:8057-03 <br /> 2 April 2015 Site Visit Memorandum <br /> 3 , <br /> u <br /> t <br /> � r <br /> �_ I <br /> t - <br /> Figure 4:Typical Rebar Cage <br /> The Contractor had also begun work on tying the rebar and forming for concrete pour 3.This pour will <br /> consist of the overhang portion of the pile cap between WP1 and WP2 and the backwall of the viewing <br /> platform portion of the pile cap along Segment A.The shaded areas in Figures 5 and 6 show the extent <br /> of concrete pour 3. <br /> Figures 7 through 9 show the progress of the rebar installation and the set-up of the form work. Overall <br /> the rebar appears to be installed per the contract documents. Remaining items include: <br /> • Drip groove <br /> • Lower layer of#4 bars perpendicular to the CL of the pile cap <br /> • Electrical conduit <br /> • PVC sleeves for dowels on the backside of the pile cap <br /> • Formwork <br /> „1, 4 <br />