Laserfiche WebLink
1-09.11A(3)D Third Party Caused Delays and Force Majeure <br /> 1-09.11A(3)D1 Caused Solely by Third Parties or Force Majeure <br /> ' 1-09.11A(3)Dla Adjustment of Contract Sum <br /> The City and the Contractor shall not be responsible to compensate each other <br /> financially for any Delay solely caused by a third party for whom neither the <br /> ' Contractor nor the City is responsible, or for any Delay caused solely by <br /> earthquake, flood, natural disasters, acts of war or acts of terrorism. A Delay <br /> caused by a utility's failure to provide service or relocate its lines (despite a <br /> ' timely request for such service or relocation)is an example of this kind of Delay <br /> for which neither the Contractor nor the City is financially responsible to the <br /> other.Mislocated utility lines or utility lines not located are another example of a <br /> ' Delay for which neither the Contractor nor the City is responsible to the other. <br /> However, the Contractor's failure to request a utility locate or relocation in a <br /> timely way is not, and any resulting Delay would be the responsibility of the <br /> Contractor. Because the Contractor is responsible for ordering materials and <br /> ' Equipment,Contractor shall not be entitled to an adjustment of Contract Time or <br /> Contract Sum due to Delays caused by the lack of materials or Equipment. A <br /> strike,job action, slowdown,work to rule,or other job action or labor dispute or <br /> problem is not a Delay caused by a third party. <br /> 1-09.11A(3)D 1 b Adjustment of Contract Time <br /> The Contractor shall be entitled to an extension of Contract Time for Delays <br /> ' caused solely by a third party for whom neither the Contractor nor the City is <br /> responsible, or for any Delay caused solely by earthquake, flood, natural <br /> disasters, acts of war or acts of terrorism. Extension of Contract Time shall be <br /> ' determined pursuant to 1-08.8 EXTENSIONS OF TIME. <br /> 1-09.11A(3)E Delays Caused Concurrently by Third Parties and Contractor <br /> or City <br /> If a Delay is caused concurrently by(a)a third party, earthquake, flood, natural disasters, <br /> acts of war or acts of terrorism and (b) either the Contractor or the City, then the <br /> Contractor or City is only responsible for the amount of Delay it caused in excess of the <br /> Delay caused by the a third party, earthquake, flood, natural disasters, acts of war or acts <br /> of terrorism. <br /> 1-09.11A(3)E1 Adjustment of Contract Sum <br /> The Contractor shall be entitled to an adjustment of Contract Sum for any Delay <br /> concurrently caused by a third party and the City, but only to the extent Contractor <br /> clearly and convincingly demonstrates that the City caused the Delay to be longer <br /> than it would have been had it been caused solely by the third party. <br /> 1-09.11A(3)E2 Adjustment of Contract Time <br /> The Contractor shall be entitled to an adjustment of Contract Time for any Delay <br /> ' concurrently caused by a third party and the City, but only to the extent Contractor <br /> clearly and convincingly demonstrates that the City caused the Delay to be longer <br /> than it would have been had it been caused solely by the third party. <br /> 1-09.11A(4) Extended or Unabsorbed Overhead <br /> 1-09.11A(4)A General <br /> To present a request for additional compensation for Extended or Unabsorbed Overhead, <br /> ' the Contractor has the burden of keeping and maintaining accurate documentation to <br /> support any such claim. If the Contractor fails to provide or keep inadequate fmancial <br /> data for an accurate and fair Eichleay calculation, Contractor waives and releases any <br /> ' claim for Unabsorbed or Extended Overhead. In presenting any claim under this section <br /> HAYES STREET REGULATOR February,2017 <br /> AND CSO CONTROLS (SRO1, SRO2,AND SRO3) <br /> WO No—UP3398-31 SP- 128 <br />