Laserfiche WebLink
Project: Pacific &Broadway/Citywide Safety <br /> Improvement Projects <br /> Change Order No.: 2 <br /> Change Order Effective Date: 03-10-2017 <br /> CONTRACTOR <br /> By i. Date: 3/20/2017 <br /> D el Rojas, VP Officer <br /> Exhibit A—Description of Changed Work <br /> This change adds working days. There are no cost associated with the added days <br /> Exhibit B—Justification: <br /> The 45 working days in the base contract anticipated a working day suspension to accommodate long <br /> lead time electrical materials. Due to multiple weather dependent tasks, in order to allow these task to <br /> move forward on workable days the working day suspension was not utilized resulting in an increase <br /> in the number of working days. <br /> Exhibit C—Additional Contract Time: <br /> There are 78 additional working days associated with this change. <br /> Page 3 of 3 <br />