I <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> I <br /> The Contractor shall not proceed with any portion of the Work in areas where right of <br /> I way, easements or rights of entry have not been acquired until the Engineer certifies to <br /> the Contractor that the right of way or easement is available or that the right of entry <br /> has been received. If the Contractor is delayed due to acts of omission on the part of <br /> I the City in obtaining easements, rights of entry or right of way, the Contractor will be <br /> entitled to an extension of time. The Contractor agrees that Delay resulting from City <br /> obtaining easement or right of entry or right of way shall not be a breach of Contract. <br /> I Each property owner shall be given 48 hours notice prior to entry by the Contractor. <br /> This includes entry onto easements and private property where private improvements <br /> must be adjusted. <br /> I The Contractor shall be responsible for providing, without expense or liability to the <br /> City, any additional land and access thereto that the Contractor may desire for <br /> temporary construction facilities, storage of materials, or other Contractor needs. <br /> I However, before using any private property, whether adjoining the Work or not, the <br /> Contractor shall file with the Engineer a written permission of the private property <br /> owner, and, upon vacating the premises, a written release from the property owner of <br /> I each property disturbed or otherwise interfered with by reasons of construction <br /> pursued under this Contract. The statement shall be signed by the private property <br /> owner, or proper authority acting for the owner of the private property affected, stating <br /> I that permission has been granted to use the property and all necessary permits have <br /> been obtained or, in the case of a release, that the restoration of the property has been <br /> satisfactorily accomplished. The statement shall include the parcel number, address, <br /> and date of signature. Written releases shall be filed with the Engineer before the <br /> ICompletion Date will be established. <br /> 1-07.27 No Waiver of State's Legal Rights <br /> I Delete 1-07.27 and substitute the following: <br /> 1-07.27 No Waiver of City's Legal Rights <br /> (******) <br /> I The City shall not be precluded or estopped by any measurement, estimate, or certificate <br /> made either before or after the completion and acceptance of the Work and payment <br /> therefor from showing the true amount and character of the Work performed and materials <br /> I furnished by the Contractor, or from showing that any such measurement, estimate, or <br /> certificate is untrue or incorrectly made, or that the Work or materials do not conform in fact <br /> to the Contract. The City shall not be precluded or estopped, notwithstanding any such <br /> 1 measurement, estimate, or certificate, and payment in accordance therewith, from <br /> recovering from the Contractor and the Sureties such damages as it may sustain by reason <br /> of the Contractor's failure to comply with the terms of the Contract. Neither the acceptance <br /> I by the Engineer nor any payment for the whole or any part of the Work, nor any extension <br /> of time, nor any possession taken by the City shall operate as a waiver of any portion of the <br /> Contract or of any power herein reserved or any right to damages herein provided, or bar <br /> recovery of any money wrongfully or erroneously paid to the Contractor. A waiver of any <br /> Ibreach of the Contract shall not be held to be a waiver of any other or subsequent breach. <br /> The Contractor and the City recognize that the impact of overcharges to the City by the <br /> Contractor resulting from antitrust law violations by the Contractor's suppliers or <br /> I Subcontractors adversely affects the City rather than the Contractor. Therefore, the <br /> Contractor agrees to assign to the City all claims for such overcharges. <br /> ISewer Regulators R4 and Division 1 -GENERAL REQUIREMENTS May 2017 <br /> R39 Modifications <br /> 1 WO No-UP3633 SP-91 <br />