Project: Hot Mix Asphalt Asphalt Overlay-2017 <br /> Change Order No. 1 <br /> Change Order Effective Date: September 11, 2017 <br /> 4. The duration of the Contract shall be adjusted to the extent described in this Change <br /> Order. <br /> 5. Contractor waives and releases any and all claims arising out of,or related to, this <br /> Change Order,the work described in Exhibit A, and all work and actual or constructive <br /> changes that occurred or began prior to the date of this Change Order,including,but <br /> not limited to,claims for equitable adjustment of time and compensation,delay,impact, <br /> overhead,or inefficiencies. This provision does not apply to requests for equitable <br /> adjustment of time or price for which the Contractor timely and properly provided <br /> notice of a differing site condition,protest,dispute, claim or Contract Claim as required <br /> by the Contract Documents. If the Contract Documents establish a time period for <br /> notice of a differing site condition,protest, dispute, claim,or Contract Claim that ends <br /> after the date of this Change Order, but relates to work performed prior to the date of <br /> this Change Order, then this provision does not apply if the Contractor timely and <br /> properly submits such notice <br /> 6. This Change Order only changes the contract between Contractor and City to the <br /> extent explicitly provided herein. <br /> CITY <br /> Attest: Approved As to Form: <br /> r....., i / , ,-,.l .n .) <br /> M.,�,r City Cl• City Atto <br /> Date: q(1-41(11,11- Date: ' i I/.-- Date: 17022//9-- <br /> Recommended By: <br /> Construction Project Engineer (if Engineering Department Director <br /> Manager(if applicable) Manager(if �, <br /> applicable) applicable) / <br /> A,i/1/ <br /> . / V. // <br /> Date: `, Zep: Date: al )1te: 9-ZS-1 Date: ' / M <br /> CONTRACTOR <br /> By A. �4446„, Date: 69.18.2-1,tt <br /> e, oYttt.a' Officer <br /> Page 2 of 7 <br />