Laserfiche WebLink
Project: Hot Mix Asphalt Asphalt Overlay-2017 <br /> Change Order No. 1 <br /> Change Order Effective Date: September 11, 2017 <br /> Exhibit D-Cost Summary: <br /> CHANGE ORDER 1 SUMMARY <br /> Unit <br /> # ITEM DESCRIPTION UNIT Adjustment $$/UNIT AMOUNT <br /> Revised Items <br /> 2 Flaggers Hour 735 $74.00 $54,390.00 <br /> 4 LIMA Class 1/2 Inch,PG 64-22 Ton 965 $70.00 $67,550.00 <br /> 5 Adjust Manhole to Grade EA -100 $100.00 ($10,000.00) <br /> 6 Adjust Catch Basin/Inlet to Grade EA -200 $100.00 ($20,000.00) <br /> 7 Adjust Valve Box to Grade EA -50 $100.00 ($5,000.00) <br /> 8 Adjust Existing Monument Casing EA -50 $70.00 ($3,500.00) <br /> 9 Planing Bituminous Pavement SY 12,000 $2.70 $32,400.00 <br /> 10 Vehicle Loop Detectors LF -1,140 $12.50 ($14,250.00) <br /> 12 Temporary Pavement Markings LF 59,000 $0.10 $5,900.00 <br /> 13 Plastic Wide Line LF 2,750 $2.00 $5,500.00 <br /> .14 Plastic Traffic Arrow EA 50 $136.00 j $6,800.00 <br /> 15 24"Plastic Crosswalk Line LF 1,070 $10.00 $10,700.00 <br /> 18 Plastic Line LF 3,750 $1.00 $3,750.00 <br /> 19 Profiled Plastic Line LF -1,750 $1.50 ($2,625.00) <br /> 22 Conduit Pipe,2"Diameter LF -600 $23.00 ($13,800.00) <br /> 23 Removing Concrete Sidewalk SY -125 $87.00 ($10,875.00) <br /> 24 Cement Concrete Sidewalk SY -160 $217.00 ($34,720.00) <br /> 25 Resolve Above Ground Conflicts Est. 38,000 $1.00 $38,000.00 <br /> 26 Uniformed Police Officer Hour 775 $95.00 $73,625.00 <br /> 27 Street Cleaning Hour 232 $205.00 $47,560.00 <br /> 28 Portable Changeable Message Sign Hour 2,300 $3.00 $6,900.00 <br /> Subtotal Revised Items $238,305.00 <br /> New Bid Items <br /> 101 OT Flagging Premium Hour 75 $71.00 $5,325.00 <br /> 102 HMA Weekend Premium TN 800 $11.25 $9,000.00 <br /> 103 Plastic ADA Symbol EA 4 $160.00 $640.00 <br /> Subtotal New Bid Items $14,965.00 <br /> New Schedule B-Broadway Water Q <br /> 2 Flaggers Hour 165 $74.00 $12,210.00 <br /> 4 HMA Class 1/2 Inch,PG 64-22 Ton 485 $70.00 $33,950.00 <br /> 7 Adjust Valve Box to Grade EA 16 5100.00 i $1,600.00 <br /> 9 Planing Bituminous Pavement SY 4,011 $2.70 $10,829.70 <br /> 10 Vehicle Loop Detectors LF 1,140 $12.50 $14,250.00 <br /> 12 Temporary Pavement Markings LF 16,000 $0.10 i $1,600.00 <br /> 15 24"Plastic Crosswalk Line LF 30 $10.00 ! $300.00 <br /> 16 24"Plastic Stop Bar LF 15 $10.00 $150.00 <br /> 17 Paint Line LF 2,650 $0.25 $662.50 <br /> 19 Profiled Plastic Line LF 4,000 51.50 $6,000.00 <br /> 22 Conduit Pipe,2"Diameter LF 50 $23.00 $1,150.00 <br /> 25 Resolve Above Ground Conflicts Est. 20,000 $1.00 $20,000.00 <br /> 26 Uniformed Police Officer Hour 25 $95.00 $2,375.00 <br /> 27 Street Cleaning Hour 3 $205.00 $615.00 <br /> Subtotal New Schedule B-Broadway Water Q 1 $105,692.20 <br /> TOTAL CHANGE ORDER#1 $358,962.20 <br /> Page 7 of 7 <br />