Laserfiche WebLink
Attachment 5 <br /> PROJECT DEVELOPMENT SCHEDULE (Revised) <br /> Sub-Grantee: City of Everett <br /> PROJECT TITLE: City of Everett Water Filter Plant Operations Building: Structural and Nonstructural <br /> Seismic Retrofit <br /> DESCRIPTION OF ACTIVITY/TASK SCHEDULED COMPLETION DATE <br /> Design & Permits September 2016 <br /> Advertisement &Award of Construction April 2017 <br /> Construction December 2017 <br /> Total Time Required to Complete This Project: 25 months <br /> October 15, 2014 <br /> January 15, 2015 <br /> April 15, 2015 <br /> July 15, 2015 <br /> October 15, 2015 <br /> Quarterly Reports Due on Project Progress, Final January 15, 2016 <br /> Project Report and all documentation, site visits and April 15, 2016 <br /> July 15, 2016 <br /> inspections. October 15, 2016 <br /> January 15, 2017 <br /> April 15, 2017 <br /> July 15, 2017 <br /> October 15, 2017 <br /> Final Report January 15, 2018 <br /> Page 2 of 2 City of Everett <br /> D15-002 Amendment A <br />