CITY OF EVERETT SPECIAL PROVISIONS
<br /> Measurement and Payment: Unit Price per Ton (TON)
<br /> Measurement for Foundation Material, Class A or B shall be by the ton, recorded on
<br /> certified weight tickets in accordance with 1-09.2 WEIGHING EQUIPMENT, and placed
<br /> within the limits of dimensions defined in the Work, descriptions for other bid items, shown
<br /> on the Plans, or COE Standard Drawings, or as otherwise approved by the Engineer.
<br /> The unit price bid per ton shall constitute full compensation for all labor, tools, materials and
<br /> equipment required to furnish, place, and compact foundation material as specified in the
<br /> Standard Specifications, these Special Provisions and as shown on COE Standard
<br /> Drawing No. 610.
<br /> The unit price for this bid item includes all costs for dewatering and over-excavation,
<br /> removal, haul, and disposal of unsuitable subgrade material below the pipe zone or
<br /> roadway subgrade.
<br /> Bid Item 15 - Gravel Borrow
<br /> Measurement and Payment: Unit Price per Ton (TON)
<br /> Measurement for Gravel Borrow shall be by the ton, recorded on certified weight tickets in
<br /> accordance with 1-09.2 WEIGHING EQUIPMENT, and placed within the limits of
<br /> dimensions defined in the Work, descriptions for other bid items, shown on the Plans, or
<br /> COE Standard Drawings, or as otherwise approved by the Engineer.
<br /> ■ Measurement for gravel borrow shall be limited to maximum trench widths defined in the
<br /> work descriptions for other bid items.
<br /> The unit price per ton, based on certified weight tickets, for gravel borrow shall be full
<br /> compensation for all labor, material, tools and equipment necessary to furnish imported
<br /> gravel borrow for trench backfill where Engineer has determined native soils are not
<br /> suitable for backfill, and other Work as required, from a Contractor-supplied source in
<br /> accordance with 2-03.3(14)J of the Standard Specifications and these Special Provisions.
<br /> The unit price for gravel borrow shall include all costs of furnishing, hauling, stockpiling,
<br /> placing, grading and compacting the material in place.
<br /> The unit price for this bid item includes all costs for removing, loading and disposing of
<br /> displaced unsuitable material, including haul.
<br /> Bid Item 16 - Ductile Iron Pipe For Water Main, 8-Inch Diam.
<br /> Measurement and Payment: Unit Price per Linear Foot (LF)
<br /> I Per linear foot pipe measurement shall be based on the slope distance from point to point.
<br /> The point of beginning or ending of measurement in any particular run of pipe shall be the
<br /> vertical intersection of the centerline of the pipe measured with the centerline of the
<br /> intersection pipe, or with the beginning or ending of any new linear length of valves or
<br /> couplings contained within the measured length. At changes in pipe size connected by a
<br /> reducer, the point of measurement shall be taken as the midpoint of the reducer.
<br /> The unit contract price for Ductile Iron Pipe For Water Main, =Inch Diam., shall constitute
<br /> full compensation for all labor, materials, tools and equipment necessary to furnish and
<br /> install the pipe, restrained joints (where shown on the Plans or as required by the Standard
<br /> Specifications and Special Provisions), and all fittings, including tees, crosses, reducers,
<br /> couplings, and sleeves required for complete installation along the run of each pipe size, as
<br /> shown on the Plans and specified herein, and additionally, shall include, but not be limited
<br /> to, the following:
<br /> 1. Removal of structures or obstructions not specifically covered under other Bid Items.
<br /> This shall include, but not be limited to, removal and disposal of the existing asphalt
<br /> Water Main Replacement"S" Division B—BID DESCRIPTIONS January 29, 2018
<br /> WONo.—UP3664 SP-7