Laserfiche WebLink
I <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> 111 <br /> DIVISION B - BID ITEM DESCRIPTIONS <br /> SCHEDULE A —WATER MAIN <br /> Bid Item 1 - Mobilization <br /> IMeasurement and Payment: Lump Sum (LS) <br /> The lump sum bid for mobilization shall constitute complete compensation for all of <br /> Contractor's preconstruction costs of preparatory work and operations including, but not <br /> limited to, those necessary for the movement of his personnel, equipment, supplies and <br /> incidentals to the Project; for the establishment of his offices, buildings and other facilities <br /> necessary for Work on this Project; for premiums on bonds and insurance for the Project, <br /> and for Work and operations that he must perform or costs he must incur before beginning <br /> production work on the various items on the Project. Mobilization also includes, but is not <br /> limited to, posting construction identification signs, securing permits, establishing safety <br /> and security measures, preparing a traffic control plan(s), preconstruction photographs, <br /> developing a Schedule of Values for lump sum bid items, submitting the project schedule <br /> and providing product and material submittals. Also include mobilization costs for all <br /> subcontracted work along with all costs for utility coordination noted on the Plans and in the <br /> Specifications. <br /> Items not included in this item include, but are not limited to: <br /> (a) Work covered by a specific bid item or Work that is to be included in a bid item <br /> or items. <br /> (b) Profit, interest on borrowed money, overhead or management costs. <br /> Partial payments will be made for the lump sum contract price for"Mobilization" as follows: <br /> (a) When 5% of the total original contract amount is earned from other bid items, <br /> 50% of the amount bid for mobilization, or 5% of the total original contract <br /> amount, whichever is the least, will be paid. <br /> (b) When 10% of the total original contract amount is earned from other bid items. <br /> 100% of the amount bid for mobilization, or 10% of the total contract amount, <br /> whichever is the least, will be paid. <br /> Upon completion of all work on the project, payment of any amount bid for mobilization in <br /> excess of 10% of the total original contract amount will be paid. <br /> Bid Item 2 - SPCC Plan <br /> Measurement and Payment: Lump Sum (LS) <br /> The lump sum bid for the Spill Prevention, Control and Countermeasures (SPCC) Plan <br /> includes, but is not limited to, all costs associated with complying with the requirements of <br /> Section 1-07(15).1 of the Standard Specification. <br /> Bid Item 3 - Force Account <br /> Measurement and Payment: Force Account (FA) <br /> This Force Account bid item shall be accomplished in accordance with 1-09.6 FORCE <br /> ACCOUNT; except, as modified below. <br /> The Force Account bid item has been included for specific miscellaneous work items listed <br /> below and for any additional work directed by the Engineer that is not required by the <br /> original Contract and to address changed conditions or unanticipated work. The amount <br /> indicated in the Proposal for this bid item is to provide a common bid amount. The actual <br /> amount paid under this bid item may vary from no payment to the full amount of the bid <br /> Water Main Replacement"Q" Division B-BID DESCRIPTIONS February 9, 2018 <br /> -Evergreen Way Rebid <br /> WO No.-UP3612 SP-3 <br /> I <br />