I <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> DIVISION B - BID ITEM DESCRIPTIONS <br /> Bid Item 1 - Mobilization <br /> Measurement and Payment: Lump Sum <br /> The lump sum bid for mobilization shall constitute complete compensation for all of <br /> Contractor's preconstruction costs of preparatory work and operations including, but not <br /> limited to, those necessary for the movement of his personnel, equipment, supplies and <br /> incidentals to the Project; for the establishment of his offices, buildings and other facilities <br /> necessary for Work on this Project; for premiums on bonds and insurance for the Project, <br /> and for Work and operations that he must perform or costs he must incur before beginning <br /> production work on the various items on the Project. Mobilization also includes, but is not <br /> limited to, posting construction identification signs, securing permits, establishing safety <br /> and security measures, preparing health and safety plan and perform employee hazard <br /> awareness training, preparing air monitoring and dust control plan, preparing a traffic <br /> control plan(s), preconstruction photographs, developing a Schedule of Values for lump <br /> sum bid items, submitting the project schedule and providing product and material <br /> submittals. Also include mobilization costs for all subcontracted work along with all costs for <br /> utility coordination noted on the Plans and in the Specifications. <br /> The lump sum bid item also includes, but is not limited to, all costs associated with <br /> furnishing all labor, tools, materials and equipment necessary for utility locating and <br /> potholing to confirm existing utility locations and depths prior to the start of construction <br /> where required in the plans. <br /> Items not included in this item include, but are not limited to: <br /> (a) Work covered by a specific bid item or Work that is to be included in a bid item <br /> or items. <br /> (b) Profit, interest on borrowed money, overhead or management costs. <br /> Partial payments will be made for the lump sum contract price for"Mobilization" as follows: <br /> (a) When 5% of the total original contract amount is earned from other bid items, <br /> 50% of the amount bid for mobilization, or 5% of the total original contract <br /> amount, whichever is the least, will be paid. <br /> (b) When 10% of the total original contract amount is earned from other bid items. <br /> 100% of the amount bid for mobilization, or 10% of the total contract amount, <br /> whichever is the least, will be paid. <br /> Upon completion of all work on the project, payment of any amount bid for mobilization in <br /> excess of 10% of the total original contract amount will be paid. <br /> Bid Item 2 - Surveying <br /> Measurement and Payment: Lump Sum <br /> Measurement for surveying will be the ratio of actual pipe installed and backfilled to the <br /> total quantity of pipe listed in the Proposal. <br /> The lump sum bid for surveying includes, but is not limited to, all costs associated with <br /> furnishing all labor, tools, survey instruments materials, and other equipment necessary for <br /> the setting and monitoring the location, elevation, alignment and grade of the Work as <br /> specified in 1-05.4 CONFORMITY WITH AND DEVIATIONS FROM PLANS AND STAKES <br /> and the Plans. <br /> The lump sum bid item also includes, but is not limited to, all costs associated with <br /> furnishing all labor, tools, survey instruments, materials and other equipment necessary for <br /> North Wetmore Stormwater Separation February, 2018 <br /> WO No—UP3659 Division B—BID ITEM DESCRIPTIONS <br /> ' SP-3 <br />