Project: Grand Avenue Park Bridge <br /> Change Order No.: 4 <br /> Change Order Effective Date: 5-08-2018 <br /> CONTRACTOR <br /> 7(1,_ <br /> By Date: May 8, 2018 <br /> Officer <br /> Exhibit A—Description of Changed Work <br /> • BNSF completed the RR crossing on January 24, 2018 for access to the bottom of the hillside. <br /> Interwest Construction, Inc (ICI) coordinated with BNSF and were ready to mobilize on <br /> January 29, 2018 to begin the work. BNSF was unable to provide a RR Flagger for the <br /> operation. BNSF was not able to provide a RR Flagger until March 14, 2018 resulting in a <br /> delay of 30 working days to the project. <br /> Exhibit B—Additional Contract Time: <br /> There are thirty(30)working days to be added to the project <br /> Exhibit C—Existing and New Bid Item(s) <br /> This is a No Cost Change Order. <br /> Measurement and Payment <br /> N/A <br /> ATTACHMENT ONE FOLLOWS(Additional Page) <br /> • Jnterwest Change Serial Letters Regarding BNSF Delay <br /> Page 3 of 3 <br />