I <br /> '1 <br /> the Contractor or its surety from any obligation under the Contract or under the <br /> payment and performance bond. <br /> 9.2 Payment for Changes <br /> A. Changes in Estimated Quantities of Unit Price Work <br /> 1. Contractor will be paid only for the actual quantities of Work performed and accepted in <br /> conformance with the Contract. When the accepted quantities of an item of Unit Price Work <br /> vary from the quantities originally estimated in the Contract Documents, payment will be at <br /> the Contract unit prices for accepted Work. If the total quantity of a Unit Price Work item <br /> varies by more than 25 percent from the quantity originally estimated in the Contract <br /> Documents,that part of the variance exceeding 25 percent may be adjusted as follows: <br /> B. Increased Quantities <br /> ' 1. Either party to the Contract will be entitled to renegotiate the price for that portion of the <br /> actual quantity in excess of 125 percent of the original Bid quantity. The price for increased <br /> quantities will be determined by agreement of the parties, or, where the parties cannot agree, <br /> ' the price will be determined by the Owner's Representative based upon the actual costs to <br /> perform the Work, including reasonable markup for Overhead and profit. <br /> C. Decreased Quantities <br /> 1. Either party to the Contract will be entitled to an adjustment of Contract Sum if the actual <br /> quantity of Work performed is less than 75 percent of the original Bid quantity. The <br /> ' adjustment of Contract Sum in the case of decreased quantities shall be based upon any <br /> increase or decrease in costs due solely to the variation of the estimated quantity. The total <br /> payment for any item will be limited to no more than 75 percent of the amount originally Bid <br /> for the item. <br /> D. Limitations <br /> ' 1. The following limitations shall apply to the adjustment: <br /> a. The equipment rates shall be actual cost but shall not exceed the rates set forth in the <br /> AGC/WSDOT Equipment Rental Agreement in effect at the time the Work is <br /> performed. <br /> b. No payment will be made for extended or unabsorbed home office Overhead and field <br /> Overhead expenses to the extent that there is an unbalanced allocation of such expenses <br /> among the Contract bid items. <br /> c. No payment for consequential damages or loss of anticipated profits will be allowed <br /> because of variance in quantities from those originally shown in the bid form, Contract <br /> provision, and Drawings. <br /> 2. When ordered by the Owner's Representative, the Contractor shall proceed with the Work <br /> pending determination of the adjustment of Contract Sum or Contract Time for the variation <br /> in quantities. <br /> ' 3. The Owner will not adjust for increases or decreases if the Owner has entered the amount for <br /> the item in the bid form only to provide a common Bid for Bidders. <br /> E. Changes in Work Not Covered By Unit Prices <br /> 1. Contractor shall be paid for changes in Work not covered by unit prices as provided in 9.5. <br /> Adjustment Of Contract Sum. <br /> ' PROCESS WATER PUMP STATION 06/13/2017 <br /> WO-3647 00 72 13 -41 <br /> I <br />