Laserfiche WebLink
CITY OF EVERETT SPECIAL PROVISIONS <br /> complete for that activity should also be shown. If during the course of construction <br /> the Contractor desires or feels it necessary to make changes in the schedule logic, <br /> these changes should be identified, highlighted, and specifically and expressly <br /> brought to the attention of the City's Representative and City along with the <br /> schedule update. <br /> An updated progress schedule shall show changes occurring since submission of <br /> the previous updated progress schedule such as: <br /> 1. Major changes in scope; <br /> 2. Activities modified since previous submission; <br /> 3. Revised projection for construction completion, as applicable; and <br /> 4. Any other changes. <br /> Contractor shall submit an updated progress schedule for review by the City and <br /> City's Representative, at the weekly construction meeting or as otherwise as <br /> requested by City's Representative or City. Any deviation from the Baseline <br /> Schedule shall be explained by the Contractor, including the cause and effect of the <br /> deviation. Contractor shall state in writing the corrective measures it will take to <br /> bring the progress of the Work back in line with the Baseline Schedule. <br /> Once an actual start or completion date is stated in a submitted progress schedule, <br /> Contractor shall not change schedule without prior written agreement of the City <br /> and City's Representative. <br /> With each submitted updated progress schedule, Contractor shall provide a written <br /> narrative report that identifies anticipated or actual deviations from the Baseline <br /> Schedule, causes of the deviations, and the impact of the deviations on the <br /> schedule and describes the corrective action taken or proposed, and its effect. <br /> 1-08.3(3) Schedule Updates <br /> Delete 1-08.3(3) and substitute the following: <br /> 1-08.3(3) Schedule Format And Content <br /> 1-08.3(3)A Schedule Format <br /> All schedules shall be in the following form: <br /> 1. Network analysis system using the current version of Microsoft Project <br /> software and the critical path method, as outlined in The Associated <br /> General Contractors of America (AGC) publication "The Use of CPM in <br /> Construction -A Manual for General Contractors." <br /> 2. Sequence of Listings: The chronological order of the start of each activity <br /> of Work. Listings on Progress Schedule and Schedule of Values shall be <br /> the same. <br /> 3. Scale and Spacing: To provide space for notations and revisions. <br /> 4. Each schedule and update shall be provided in three (3) paper copies <br /> and three (3) electronic copies in current Microsoft Project 2007 format. <br /> Paper copies shall be on a single sheet of paper and of sufficient size to <br /> allow legibility of schedule. Pieces of the schedule on separate sheets of <br /> paper that must be taped together to form schedule are not permitted. <br /> Electronic copies shall be submitted on either separate CD-ROMs or as <br /> email attachment to City's Representative. <br /> Wetmore Ave Stormwater Bypass Division 1 —GENERAL REQUIREMENTS August, 2018 <br /> WO No—UP3704 SP—1-92 <br />