My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
Interwest Construction Inc 8/9/2018
>
Contracts
>
10 Years Then Transfer to State Archivist
>
2018
>
Interwest Construction Inc 8/9/2018
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
8/14/2018 9:30:57 AM
Creation date
8/14/2018 9:30:02 AM
Metadata
Fields
Template:
Contracts
Contractor's Name
Interwest Construction Inc
Approval Date
8/9/2018
Council Approval Date
8/1/2018
End Date
10/31/2018
Department
Public Works
Department Project Manager
Amie Roshak
Subject / Project Title
Wetmore Avenue Stormwater Bypass Project
Public Works WO Number
UP3704
Tracking Number
0001358
Total Compensation
$681,696.00
Contract Type
Capital Contract
Retention Period
10 Years Then Transfer to State Archivist
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
141
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
CITY OF EVERETT SPECIAL PROVISIONS <br /> Any requests for extensions in Contract Time, whether resulting from Extra Work <br /> directed by the City or not, shall be accompanied by an analysis of schedules using the <br /> critical path method. This analysis shall include an updated schedule, an as-planned <br /> schedule, an as-built schedule, a but-for schedule, and narrative explaining the alleged <br /> causes, schedule impacts and all costs related to or arising out of the proposed <br /> extension. Any requests for extensions of Contract Time by the Contractor shall be <br /> submitted in accordance with these Contract Documents. Extensions of Contract Time <br /> will be granted only as provided in the Contract Documents and to the extent that <br /> affected critical activities exceed the Total Float time along the affected paths of the <br /> reviewed Preliminary Schedule at the time the change was authorized in writing by the <br /> City. Contractor has the burden of clearly and convincingly demonstrating entitlement <br /> to any adjustment of Contract Time. <br /> If the City is solely responsible for any Delay to Substantial Completion, Physical <br /> Completion, Completion Date, or Final Acceptance, the Contractor shall only be entitled <br /> to compensation or other damages as described in 1-09.11A REMEDIES, provided that <br /> Contractor timely gave Notice pursuant to 1-04.5 NOTICE BY CONTRACTOR, timely <br /> submitted a Contract Claim pursuant to 1-09.11(2) CONTRACT CLAIMS and fulfilled the <br /> requirements of 1-08.3 PROGRESS SCHEDULE. <br /> 1-08.9 Liquidated Damages <br /> Delete the definition for"T" in the Liquidated Damages Formula and substitute the following: <br /> T = original time for Substantial Completion <br /> Delete the fourth sentence of the fourth paragraph of 1-08.9 and substitute the following: <br /> For overruns in Contract Time occurring after the Physical Completion Date, liquidated <br /> damages shall be assessed at the rate of ten (10) percent of the amount computed by <br /> the formula in this section until the actual Physical Completion Date of all the Contract <br /> Work. <br /> 1-08.10 Termination of Contract <br /> 1-08.10(1) Termination for Default <br /> Delete all of 1-08.10(1) and substitute the following: <br /> The City may terminate the Contract upon written notice to Contractor and its Surety <br /> whenever the Contractor is deemed to be in default or fails to fulfill, in a timely and <br /> proper manner, one or more Contract obligations, or is in violation of any provisions <br /> or covenants of the Contract. Termination shall be effective upon Contractor's and <br /> Surety's receipt of such notice <br /> For purposes of this section, the Contractor shall be deemed to be in default upon <br /> the occurrence of one or more of the following events: <br /> 1. If Contractor is bankrupt or insolvent. <br /> 2. If Contractor makes a general assignment for the benefit of creditors. <br /> 3. If a trustee or receiver is appointed for Contractor, or for any of <br /> Contractor's property. <br /> 4. If Contractor files a petition to take advantage of any debtor's law, or to <br /> reorganize under any bankruptcy chapter or law. <br /> 5. If Contractor repeatedly fails to make prompt payments to subcontractors <br /> or others for labor, materials, or Equipment. <br /> 6. If Contractor disregards laws, ordinances, rules, regulations, or orders of <br /> public bodies having jurisdiction. <br /> 7. If Contractor disregards the authority of the City or City's Representative. <br /> Wetmore Ave Stormwater Bypass Division 1 —GENERAL REQUIREMENTS August, 2018 <br /> WO No—UP3704 SP—1-99 <br />
The URL can be used to link to this page
Your browser does not support the video tag.