Laserfiche WebLink
1 <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> 2. Roadway drainage along and under the traveled Roadway, sidewalk, path or <br /> detour, and <br /> 3. All barricades, signs, and lights needed for directing traffic through the <br /> temporary Roadway. sidewalk, path or detour in the construction area. <br /> The Contractor shall protect and maintain all other Work in areas not used by traffic. <br /> All costs associated with protecting and maintaining such Work shall be the I <br /> responsibility of the Contractor except those costs associated with implementing the <br /> TESC Plan according to Section 8-01. <br /> After suspension during which the City has done the routine maintenance, the I <br /> Contractor shall accept the traveled Roadway, sidewalk, path or detour as is when <br /> Work resumes. The Contractor shall make no claim against the City for the condition <br /> of the Roadway or detour. <br /> After any suspension, the Contractor shall resume all responsibilities the Contract <br /> assigns for the Work. <br /> 1-08.8 Extensions of Time 1 <br /> Delete the first and second sentences in the second paragraph of 1-08.8. <br /> Supplement 1-08.8 by adding the following: <br /> Any requests for extensions in Contract Time, whether resulting from Extra Work <br /> directed by the City or not, shall be accompanied by an analysis of schedules using the <br /> critical path method. This analysis shall include an updated schedule, an as-planned <br /> schedule, an as-built schedule, a but-for schedule, and narrative explaining the alleged <br /> causes, schedule impacts and all costs related to or arising out of the proposed <br /> extension. Any requests for extensions of Contract Time by the Contractor shall be <br /> submitted in accordance with these Contract Documents. Extensions of Contract Time <br /> will be granted only as provided in the Contract Documents and to the extent that <br /> affected critical activities exceed the Total Float time along the affected paths of the <br /> reviewed Preliminary Schedule at the time the change was authorized in writing by the ' <br /> City. Contractor has the burden of clearly and convincingly demonstrating entitlement <br /> to any adjustment of Contract Time. <br /> If the City is solely responsible for any Delay to Substantial Completion, Physical ' <br /> Completion, Completion Date, or Final Acceptance, the Contractor shall only be <br /> entitled to compensation or other damages as described in 1-09.11A REMEDIES, <br /> provided that Contractor timely gave Notice pursuant to 1-04.5 NOTICE BY <br /> CONTRACTOR, timely submitted a Contract Claim pursuant to 1-09.11(2) CONTRACT <br /> CLAIMS and fulfilled the requirements of 1-08.3 PROGRESS SCHEDULE. <br /> 1-08.9 Liquidated Damages , <br /> Revise the fourth paragraph of 1-08.9 to read as follows: <br /> When the Contract Work has progressed to Substantial Completion as defined in the <br /> Contract, the Engineer may determine that the work is Substantially Complete. The <br /> Engineer will notify the Contractor in writing of the Substantial Completion Date. For <br /> overruns in Contract time occurring after the date so established, the formula for <br /> liquidated damages shown above will not apply. For overruns in Contract time ' <br /> occurring after the Substantial Completion Date, liquidated damages shall be assessed <br /> on the basis of direct engineering and related costs assignable to the project until the <br /> actual Physical Completion Date of all the Contract Work. The Contractor shall <br /> complete the remaining Work as promptly as possible. Upon request by the Project <br /> Engineer, the Contractor shall furnish a written schedule for completing the physical <br /> Work on the Contract. <br /> Watermain Replacement"T" Division 1 —GENERAL REQUIREMENTS October 10, 2018 <br /> WO No—UP3684 SP—106 <br /> 111 <br />