EXHIBIT Cl <br /> TIME SCHEDULE OF COMPLETION <br /> City of Everett <br /> Replacement of Reservoir 2 <br /> Work Order #UP3658 <br /> PHASE 2 - FINAL DESIGN AND BIDDING <br /> Preliminary Estimated Schedule <br /> Murraysmith will begin work upon receipt of Notice to Proceed from the City and proceed <br /> according to the estimated schedule below. However, the schedule may change due to factors <br /> beyond Murraysmith's control. <br /> Final Design Tasks Estimated Completion <br /> Notice to Proceed Jan 2019 <br /> Task 103—Project Management Jan 2019—July 2020 <br /> Task 221—City Coordination Jan 2019—July 2020 <br /> Task 222—Subconsultant Coordination Jan 2019—July 2020 <br /> Task 223—Public Outreach Support Feb 2019—April 2020 <br /> Task 224—Permitting Support Feb 2019—April 2020 <br /> Task 225—Final Design Feb 2019—April 2020 <br /> 60%Design Submittal Feb-June 2019 <br /> Project hold during SEPA completion* July-Sept 2019 <br /> 90%Design Submittal Oct 2019-Jan 2020 <br /> 99%Design Submittal Feb -March 2020 <br /> 100%Design Submittal April2020 <br /> Task 226—Bidding Support May—July 2020 <br /> Task 227—Subconsultant Services Jan 2019—July 2020 <br /> Task 228—Unanticipated Labor or Expenses As Requested by City <br /> Estimated Construction Tasks** Estimated Completion <br /> Construction Aug 2020—Dec 2021 <br /> * Final design schedule reflects a 3-month pause following the 60%submittal to complete SEPA. <br /> ** Preliminary estimate of construction schedule provided. <br /> City of Everett MURRAYSMITH Replacement of Reservoir 2 <br /> November 29, 2018 Final Design Pagel <br />