5. The Contractor believes it is required or directed to perform work that is outside the <br /> 1 <br /> scope of the Contract Documents; or <br /> 6. An event occurs, or fails to occur,that the Contractor believes, or should reasonably <br /> foresee, may result in a Contract Claim; <br /> the Contractor shall immediately give Notice to the Owner or Owner's Representative as provided in this <br /> section and elsewhere in the General Conditions and Specifications. <br /> Timely and adequate Notice is a condition precedent to a Contract Claim. ' <br /> Requests for extensions of Contract Time must be made and will be evaluated in accordance with <br /> sections 5.2.2.2 Extensions of Contract Time. <br /> Irrespective of any request for additional compensation or Contract Time or any Contract Claim that work <br /> is extra and not part of the original scope of work, the Contractor shall proceed expeditiously and <br /> promptly with the work as the Owner orders. <br /> If the Contractor fails to follow the procedures of this Contract, including failing to give Notice, the <br /> Contractor completely waives any Contract Claims. In its sole discretion, the Owner may waive strict <br /> compliance with procedures, but any such waiver of one or more items or elements does not waive the <br /> necessity for Contractor's strict compliance with any other item or element, nor shall such waiver be <br /> admissible in any legal proceeding for any reason. <br /> 10.2 FORM OF NOTICE <br /> The Notice must include the following minimum information: <br /> 1. A complete and accurate description of the event(s)giving rise to the Notice, including <br /> dates, times, and locations; <br /> 2. A preliminary list of persons of involved in such event; <br /> 3. A statement whether the Contractor believes the event may result in a Contract Claim for <br /> additional Contract Time or adjustment of the Contract Sum; <br /> 4. A date by which Contractor shall begin providing Supplemental Information as provided in <br /> this section. <br /> 10.3 SUPPLEMENTAL INFORMATION <br /> Contractor shall supplement the written Notice as soon as possible with a written statement providing the <br /> following: <br /> 1. The date of the event, incident, direction, etc.; <br /> 2. The nature and circumstances giving rise to the Notice; <br /> 3. The Contract provisions relating to the event, incident, direction, etc.; <br /> 4. The estimated dollar cost, if any, of the Extra Work, delay, etc. and how that estimate <br /> was determined; and <br /> 5. An analysis of the progress schedule showing the schedule change or disruption if the <br /> Contractor is asserting a schedule change or disruption; <br /> Throughout any work related to a Notice, the Contractor shall keep complete and accurate records of <br /> costs, expenses, and time incurred for which Contractor will or may seek an adjustment. Contractor <br /> waives and is stopped from seeking an adjustment of Contract Sum or Contract Time where Contractor <br /> fails to keep and maintain cost, timekeeping, and scheduling records segregated and contemporaneously <br /> allocated to the subject work for which an adjustment is sought. For example, failure to keep <br /> contemporaneous labor and Equipment time records specifically and only allocated to each item of <br /> claimed Extra Work shall constitute a waiver of any Contract Claim for reimbursement or additional <br /> Contract Time for each such item of Extra Work. The Contractor shall permit the Owner access to these <br /> and any other records needed for evaluating requests for additional Contract Time or Contract Sum. <br /> EVERETT RIVERFRONT SURCHARGE GENERAL CONDITIONS <br /> PHASE 3 <br /> 00710-40 <br />