CITY OF EVERETT SPECIAL PROVISIONS <br /> the Contractor shall not be entitled to any increase to the extent caused by the <br /> Contractor. <br /> 1-08.7 Maintenance During Suspension <br /> Delete all of 1-08.7 and substitute the following: <br /> Before and during any suspension (as described in Section 1-08.6) the Contractor <br /> shall protect the Work from damage or deterioration. Suspension shall not relieve the <br /> Contractor from anything the Contract requires unless this Section states otherwise. <br /> At no expense to the City, the Contractor shall provide through the construction area a <br /> safe. smooth, and unobstructed roadway, sidewalk, and path for public use during <br /> suspension. as required in 1-07.23 PUBLIC CONVENIENCE AND SAFETY. This may <br /> require a temporary road or detour. <br /> If the Engineer determines that the Contractor failed to pursue the Work diligently <br /> before the suspension, or failed to comply with the Contract or orders, then the <br /> Contractor shall maintain the temporary roadway, sidewalk, and path in use during <br /> 111 <br /> suspension. In this case, the Contractor shall bear the maintenance costs. If the <br /> Contractor fails to maintain the temporary roadway, sidewalk, and path the City will do <br /> the Work and deduct all resulting costs from payments due to the Contractor. <br /> If the Engineer determines that the Contractor has pursued the Work diligently before <br /> the suspension, then the City will maintain the temporary roadway, sidewalk, and path <br /> (and bear its cost). This City-provided maintenance work will include only routine <br /> maintenance of: <br /> 1. The Traveled Way, Auxiliary Lanes, Shoulders, detour surface. sidewalks, and <br /> paths, <br /> 2. Roadway drainage along and under the traveled Roadway. sidewalk, path or <br /> detour, and <br /> 3. All barricades, signs, and lights needed for directing traffic through the <br /> temporary Roadway, sidewalk, path or detour in the construction area. <br /> The Contractor shall protect and maintain all other Work in areas not used by traffic. <br /> All costs associated with protecting and maintaining such Work shall be the <br /> responsibility of the Contractor except those costs associated with implementing the <br /> TESC Plan according to Section 8-01. <br /> After suspension during which the City has done the routine maintenance, the 111Contractor shall accept the traveled Roadway, sidewalk, path or detour as is when <br /> Work resumes. The Contractor shall make no claim against the City for the condition <br /> of the Roadway or detour. <br /> After any suspension, the Contractor shall resume all responsibilities the Contract ' <br /> assigns for the Work. <br /> 1-08.8 Extensions of Time <br /> Delete the first and second sentences in the second paragraph of 1-08.8. <br /> Supplement 1-08.8 by adding the following: <br /> Any requests for extensions in Contract Time, whether resulting from Extra Work <br /> directed by the City or not, shall be accompanied by an analysis of schedules using the <br /> critical path method. This analysis shall include an updated schedule, an as-planned <br /> schedule, an as-built schedule, a but-for schedule, and narrative explaining the alleged <br /> causes, schedule impacts and all costs related to or arising out of the proposed <br /> extension. Any requests for extensions of Contract Time by the Contractor shall be <br /> submitted in accordance with these Contract Documents. Extensions of Contract Time <br /> Alverson Stormwater Separation February, 2019 <br /> WO No—UP3660 Division 1 —GENERAL REQUIREMENTS <br /> SP-102 <br />