Laserfiche WebLink
1.5 inches on Feb. 9, 2019 <br /> 3.5 inches on Feb. 10, 2019 <br /> 6.1 inches on Feb. 11, 2019 (daily record) <br /> Trace amounts on Feb. 12-14, 2019 <br /> The above detailed weather event impacted Faber Construction's, subcontractors' and suppliers' <br /> abilities to complete the work required to begin Critical Path items, including but not limited to <br /> mobilization activities. Due to these delays, the critical path of this project has been disrupted by <br /> 14 calendar days. Faber Construction requests the City of Everett's authorization of a No Cost <br /> Time Extension of (14) days. <br /> Per discussions with the Owner's Project Manager and the Design Team, this Time Extension will result in <br /> a revised Substantial Completion date of October 3rd, 2019. <br /> END OF SECTION 00 6363 <br />