June 23, 2017. G-4400 <br /> Underpinning Evaluation Page 4 <br /> 2514- 51"Street SW,Everett <br /> A maximum pier spacing of 5.5 feet was calculated for the east wall and a maximum pier spacing of 4.4 <br /> feet was calculated for the north wall based on the dead and live loads of the structure and using an <br /> allowable pier capacity of 13,500 lbs. The windows in the structure concentrate building loads at the <br /> northeast building corner. Building loads are also concentrated between the main entry doorway and <br /> window on the north wall. To support the concentrated loads,two piers are recommended at the <br /> northeast corner and three piers are recommended between the door and window on the north wall. <br /> Bending and shear capacity of the foundation were checked for the worst case condition and found to <br /> be acceptable for up to a 5.4 foot unsupported foundation section. The pier spacing,bending and <br /> shear calculations, are included in Appendix A. Because the house is to be lifted, we recommend a <br /> maximum spacing of 4 feet, except under the north window where foundation loads are concentrated at <br /> the ends of the windows and up to a 5.4 foot spacing is acceptable. <br /> PIER INSTALLATION DESCRIPTION <br /> The push piers are advanced into the soil with a hydraulic pump and cylinder combination using the <br /> structure as the reaction force. The hydraulic pressure is monitored with a calibrated pressure gauge <br /> during installation. When the tip of the pier reaches suitable bearing strata the hydraulic force on the <br /> pier is gradually increased to 200 percent of the design load or until movement of the design frame <br /> occurs (the foundation begins to lift). <br /> PIER LOAD TESTING&INSPECTION <br /> Installation of approximately 8 piers is anticipated. An ASTM quick test(load test)is recommended <br /> on one pier. Geotechnical inspection is recommended during pier installation and load testing to verify <br /> proper embedment to the bearing strata and to verify the pier capacities are achieved in accordance <br /> with the design. <br /> GEO Group Northwest,Inc. <br />