ORDINANCE NO. 4112
<br /> AN ORDINANCE of the City of Everett, Washington, amending
<br /> Section 2 of Ordinance No. 4057 of the city, passed and
<br /> approved November 13, 1964; amending Sections 1 and 2
<br /> of Ordinance No. 4080 of the city, passed and approved
<br /> April 6, 1965; and declaring an emergency.
<br /> THE CITY OF EVERETT DOES ORDAIN:
<br /> Section 1. That Section 2 of Ordinance No. 4057 of the City of Everett,
<br /> Washington, be and the same is hereby amended to read as follows:
<br /> "Section 2. The estimated cost of acquiring, constructing and
<br /> installing the above-described additions and improvements to the
<br /> water supply and distribution system of the City is hereby declared
<br /> to be, as near as may be, the sum of $12, 000, 000, which cost shall
<br /> be provided from the sale of water revenue bonds of the City in the
<br /> principal sum of $12, 000, 000.
<br /> As an integral part of the plan for acquiring, constructing and
<br /> installing the above-described additions and improvements to such
<br /> system the City shall issue and sell such water revenue bonds in
<br /> such amount or amounts and at such time or times as the Council
<br /> may determine to be to the best interest of the City. The exact date
<br /> or dates, form, terms,maturities and covenants of such bonds shall
<br /> be as hereafter fixed by ordinance or ordinances of the City. "
<br /> Section 2. That Section 1 of Ordinance No. 4080 of the City of Everett,
<br /> Washington, (which section amends Section 1 of Ordinance No. 4057 of the city)
<br /> be and the same is hereby amended to read as follows:
<br /> "Section 1. The following plan for the acquisition, construction,
<br /> and installation of additions and improvements to the water supply
<br /> and distribution system of the City is hereby specified and adopted,
<br /> to wit:
<br /> The City shall acquire, construct and install the following:
<br /> A water transmission line to be known as Pipe Line No. 5,
<br /> being 51 inches in diameter, constructed of steel with coal
<br /> tar enamel protective coatings, complete with valves, fittings
<br /> and appurtenances beginning at the southerly tip of LAKE
<br /> CHAPLAIN located in the NE 1/4 of Sec. 6, Twp. 28 N, R. 8
<br /> E.W.M. ; thence along and adjacent to the City's existing
<br /> pipeline No. 1 through the SE 1/4 of said Sec. 6, Twp. 28 N.,
<br /> R 8, E.W.M. ; the westerly 1/2 of Sec. 's 8 and 17, Twp. 28 N.,
<br /> R 8 E. W.M. ; the SE 1/4 of Sec. 18, Twp. 28 N. , R. 8 E. W.M. ;
<br /> the northerly 1/2 of Sec. 19, Twp. 28 N. , R. 8 E. W.M. ; the
<br /> northerly 1/2's of Sec. 's 19 through 24, Twp. 28 N., R. 7
<br /> E.W.M. ; the N.E. 1/4 of Sec. 24, Twp. 28 N. , R. 6 E. W.M. ;
<br /> the S. E. , S. W. , and N. W. 1/4's of Sec. 13, Twp. 28 N. , R. 6
<br />
|