Project: Everett Downtown Streetscape Improvement
<br /> Change Order No.1
<br /> Change Order Effective Date: October 16, 2019
<br /> New Item#A-102—Delete Electrical work on Hoyt Avenue. Add new Item#A-102 entitled,
<br /> "Delete Electrical Work on Hoyt Avenue" at the agreed to credit to the City of Everett of($23,515.00),
<br /> which results in a Contract decrease of($23,515.00).
<br /> New Item#A-103—Equitable Adjustment for Pre-Formed Loop Delay on Hoyt Avenue. Add
<br /> new Item#A-103 entitled, "Equitable Adjustment for Pre-Formed Loop Delay on Hoyt Avenue" at
<br /> the agreed to lump sum price of$31,182.00, which results in a Contract increase of$31,182.00.
<br /> New Item# B2-10—Hoyt Avenue Mid-Block Crosswalk Change. Add new item#B2-10 entitled,
<br /> "Hoyt Avenue Mid-Block Crosswalk Change" at the agreed to lump sum price of$28,407.00, which
<br /> results in a Contract increase of$28,407.00.
<br /> New Item# C-200—Controlled Density Fill (CDF). Add new item#C-200 entitled, "Controlled
<br /> Density Fill (CDF)" at the agreed to unit price of$140/Cubic Yard,by adding 150 Cubic Yards of
<br /> CDF to the Contract, resulting in a Contract increase of$21,000.00.
<br /> New Item# C-201 —Ductile Iron Pipe for Storm Drainage, 12-Inch Diameter. Add new item#C-
<br /> 201 entitled, "Ductile Iron Pipe for Storm Drainage, 12-Inch Diameter" at the agreed to unit price of
<br /> $130.00/Linear Foot,by adding 275 linear feet to the Contract, resulting in a Contract increase of
<br /> $35,750.00.
<br /> New Item# C-202—Ductile Iron Pipe for Storm Drainage, 8-Inch Diameter. Add new item#C-
<br /> 202 entitled, "Ductile Iron Pipe for Storm Drainage, 8-Inch Diameter"at the agreed to unit price of
<br /> $120.00/Linear foot,by adding 85 linear feet to the Contract, resulting in a Contract increase of
<br /> $10,200.00.
<br /> New Item# C-203—Aluminum Light Poles on Rucker Avenue. Add new item#C-203 entitled,
<br /> "Aluminum Light Poles on Rucker Avenue" at the agreed to lump sum price of$34,060.00, resulting
<br /> in a Contract increase of$34,060.00.
<br /> Modified Bid Items
<br /> Bid Item#A-17—Roadway Excavation,Including Haul. Modify existing bid item#A-17 entitled,
<br /> "Roadway Excavation, Including Haul"at the Contract unit price of$112/Cubic Yard,by adding 350
<br /> cubic yards to the Contract, resulting in a Contract increase of$39,200.00.
<br /> Bid Item# C-9—Flaggers. Modify existing bid item entitled, "Flaggers" at the Contract unit price of
<br /> $60/Hour,by adding 500 hours to the Contract, resulting in a Contract increase of$30,000.00
<br /> Bid Item#D-3—Gravel Borrow, Including Haul. Modify existing bid item#D-3 entitled, "Gravel
<br /> Borrow, Including Haul" at the Contract unit price of$46.00/Ton,by adding 825 tons to the Contract,
<br /> resulting in a Contract increase of$37,950.00.
<br /> Page 4 of 7