CITY OF EVERETT SPECIAL PROVISIONS <br /> 1 the City will notify the Contractor in writing that the Work is accepted as substantially <br /> complete. Except for any portion(s) of Work specified for early completion or required <br /> by the City for early possession, Substantial Completion will not occur for Work until the <br /> entire Project is ready for possession and use. The acceptance Notice will include a <br /> Punch List of incomplete Work items and corrective Works, set the date for their <br /> completion and repair, describes the division of responsibility between the City and <br /> Contractor, and describe other terms of acceptance. The Contractor will acknowledge <br /> receipt of the acceptance Notice in writing, indicating acceptance of all of its terms and <br /> provisions. <br /> Subsequent to the Substantial Completion date, the City may exclude the Contractor <br /> from the Work during such periods when construction activities might interfere with the <br /> intended operation of the Project. The City, however, shall allow the Contractor <br /> reasonable access for completion or correction of incomplete Punch List items. <br /> 1-08.5(3) Acceptance of Work <br /> (******) <br /> Upon completion of the Project, including, but not limited to, Record Drawings, required <br /> reports and operations and maintenance manuals, the Contractor shall so notify the <br /> City's Representative in writing. Upon receipt of the notification, the City's <br /> Representative will promptly, by personal inspection, determine the actual status of the <br /> Work in accordance with the terms of the Contract. If the City's Representative finds <br /> materials, Equipment, or workmanship that do not meet the terms of the Contract, it will <br /> prepare a Punch List of such items and submit it to the Contractor. Following completion <br /> of the corrective work by the Contractor, the City's Representative will notify the City that <br /> the Work has been completed in accordance with the Contract. The City shall make the <br /> final determination of acceptability and completion. For portions of the Project not <br /> previously accepted as substantially complete, the conditions of guarantee shall <br /> commence on the date that the City determines the Project is complete. <br /> 1-08.6 Suspension of Work <br /> Supplement 1-08.6 by adding the following: <br /> 1-08.6(1) Suspension Procedures <br /> (******) <br /> The City may, at its convenience and at any time and without cause, suspend all or any <br /> part of the Work by notice in writing to the Contractor. The Contractor shall resume the <br /> Work within five (5) calendar days after receiving written notice from the City to do so. <br /> The Contractor will be allowed an increase in the Contract Sum or an extension of <br /> Contract Time, or both, directly attributable to any suspension in accordance with the <br /> Change Order procedures in these Special Provisions; provided, the Contractor shall <br /> not be entitled to any increase to the extent caused by the Contractor. <br /> 1-08.7 Maintenance During Suspension <br /> Delete all of 1-08.7 and substitute the following: <br /> Before and during any suspension (as described in Section 1-08.6) the Contractor shall <br /> protect the Work from damage or deterioration. Suspension shall not relieve the <br /> Contractor from anything the Contract requires unless this Section states otherwise. <br /> At no expense to the City, the Contractor shall provide through the construction area a <br /> safe, smooth, and unobstructed roadway, sidewalk, and path for public use during <br /> suspension, as required in 1-07.23 PUBLIC CONVENIENCE AND SAFETY. This may <br /> require a temporary road or detour. <br /> If the Engineer determines that the Contractor failed to pursue the Work diligently before <br /> the suspension, or failed to comply with the Contract or orders, then the Contractor shall <br /> Watermain Replacement"U" Division 1 —GENERAL REQUIREMENTS October 1, 2019 <br /> WO No—UP3698 SP—101 <br /> I <br />